Ports & Terminals

Rotterdam to add 1.4 million TEU at Maasvlakte II by 2030

APM Terminals and Rotterdam port will add 1.4 million TEU via a 711-metre quay extension at Maasvlakte II, with works from October 2027 to January 2030 pending a February 2027 investment decision.

APM Terminals plans Rotterdam expansion to add 1.4 million TEU capacity - Breakbulk.News
Exhibit · APM Terminals plans Rotterdam expansion to add 1.4 million TEU capacity - Breakbulk.News — smartschwarz / pixabay

Adjustments

  1. Expansion adds approximately 1.4 million TEU annual capacity at Maasvlakte II, announced November 24, 2026.
  2. Scope: 25 hectares of terminal space, 711-metre quay wall extension, 428-metre rear crane rail extension, 1.3 million cubic metres of sand dredging.
  3. Construction provisionally runs from October 2027 to January 2030, in phases without service suspension.
  4. Port of Rotterdam Authority shareholders take the investment decision in February 2027; contract value undisclosed.
  5. TenderNed prequalification published January 2027; quay wall contract award process starts March 2027.

APM Terminals Maasvlakte II and the Port of Rotterdam Authority will add approximately 1.4 million TEU of annual container handling capacity, with construction scheduled to start in October 2027 and run until January 2030.

The partners announced the project on November 24, 2026. It develops the last available section of the terminal site along the Prinses Amaliahaven and adds 25 hectares of terminal space plus a 711-metre extension of the existing quay wall. Construction will proceed in phases, allowing current container operations to continue throughout.

The new infrastructure will accommodate deepsea container vessels, feeder services and inland waterway vessels, expanding Rotterdam's capacity to handle international container flows and distribute cargo across the European hinterland.

What does the works package include?

The Port of Rotterdam Authority will prepare the additional terminal land and build the maritime infrastructure, while APM Terminals develops terminal operations. The scope covers:

  • a 711-metre quay wall extension;
  • a 428-metre extension of the rear crane rail;
  • dredging of approximately 1.3 million cubic metres of sand.

The added quay length will give operators more flexibility in vessel scheduling and berthing arrangements, and the enlarged terminal area increases space for container handling and storage. The 711-metre extension is roughly 40 percent of the quay length at a mid-size deepsea berth.

APM Terminals has invested in the Maasvlakte II facility since 2008. An initial section of the ongoing expansion recently entered operation, and the latest phase will extend the terminal's footprint without suspending existing services.

How will automation be preserved?

Maasvlakte II runs electrified cargo handling equipment, automated transport vehicles and remotely operated quay cranes, with equipment powered by renewable electricity, according to the port authority. The terminal holds direct connections to rail and inland waterway networks, supporting container distribution to industrial and commercial centres across Europe.

The expansion is intended to absorb future container volumes while maintaining that automated operating model.

Harold Kunst, managing director of APM Terminals Maasvlakte II, said the development would create room for future growth and support the terminal's ability to serve customers safely, reliably and efficiently over the longer term. He also credited cooperation with the port authority as key to delivering the required infrastructure.

Boudewijn Siemons, CEO of the Port of Rotterdam Authority, said the additional capacity and infrastructure would strengthen Rotterdam's position in the European container market and contribute to the resilience of logistics supply chains.

When does the money get committed?

Both parties will spend the coming months finalising the technical scope, construction schedule and contracting strategy. The port authority's shareholders are expected to take the investment decision in February 2027. The financial value of the infrastructure development has not been disclosed.

Procurement moves earlier:

  • Prequalification for the construction contract is scheduled for publication through TenderNed, the Dutch public procurement platform, in January 2027.
  • The contract award process for the quay wall construction begins in March 2027.
  • Construction activities are provisionally scheduled from October 2027 until January 2030.

The proposed schedule remains subject to the investment decision and the subsequent procurement process. Until the shareholders commit, the 1.4 million TEU is a plan, not a booking.

via Google News: Ports & Terminals (Source)

Share this article:

More from Rebecca Stone

Rebecca Stone

Show full bio

News editor covering people, launches and day-to-day practice in commercial shipping for industry professionals at Vessels.

152 articles

Linked entries

  1. APM Terminals unveils 1.4m TEU Rotterdam expansion plan
  2. Mindanao Container Terminal adds 300m of berth by 2028
  3. World Bank: terminals at 72.2% utilisation, already past congestion line
  4. Rijeka picks Končar for 17.5 MW shore power at two terminals
  5. Monrovia port starts 5,482 TEU container yard expansion

▲ Previous article▼ Next article