Monrovia port starts 5,482 TEU container yard expansion
APM Terminals is adding 5,482 TEU of container storage at Monrovia and has ordered a third mobile harbour crane and five terminal trucks for May 2027 delivery as dwell hits 15-16 days.

Adjustments
- APM Terminals relocated 388 TEU of long-stay containers from the main terminal to the ro-ro yard.
- The operator is converting a car park into a stacking area for 370 TEU of empty containers.
- Planned storage totals 5,482 TEU, including a 2,800 TEU empty area not yet operational and 2,312 TEU for imports.
- Container dwell rose from seven to eight days in 2025 to about 15-16 days this year.
- Delivery of a third mobile harbour crane, three reach stackers, two empty container handlers, five terminal trucks and two spreaders is expected in May 2027.
By Amara Osei
Container dwell at Liberia’s main seaport, the Freeport of Monrovia, has reached about 15-16 days this year, up from seven to eight days in 2025, as terminal operator APM Terminals clears ground for 5,482 TEU of additional container storage.
The first relief is operational. APM Terminals has relocated 388 TEU of long-stay containers from the main terminal to the port’s ro-ro yard and is converting an existing car park into a stacking area for 370 TEU of empty containers.
Sensible housekeeping, perhaps, but no instant cure for boxes waiting around the main terminal. The relocation removes long-stay units from the main terminal; the car-park conversion creates another place to put empties. Neither measure shortens the dwell clock on its own.
What changes on the ground now?
APM Terminals has already demolished existing structures to make room for an additional 2,800 TEU of empty-container storage. The new area is not yet operational, so operators cannot treat its 2,800 TEU as capacity available now.
APM plans further demolition to provide another 2,312 TEU for import containers. Together with the 370 TEU car-park yard and the 2,800 TEU empty-container area, the three works represent 5,482 TEU of planned storage.
The 388 TEU relocation is separate from that total because it moves existing containers to the ro-ro yard rather than adding a new stacking area. The larger projects still have to move from demolition to operational use.
Because the larger yards are not yet operational, the 5,482 TEU figure describes planned space rather than capacity available now. The immediate test will be whether the 370 TEU conversion and 388 TEU relocation relieve congestion while the remaining works advance.
This sequence matters. APM can improve flow before the new areas arrive, while the larger yards remain future capacity rather than an immediate release valve.
What equipment is coming?
APM Terminals has ordered a third mobile harbour crane, three reach stackers, two empty container handlers, five terminal trucks and two spreaders. APM expects delivery of the package in May 2027.
The expected delivery date leaves the immediate yard reshuffle carrying the load. The 388 TEU move and 370 TEU conversion must provide the first relief while the 2,800 TEU and 2,312 TEU works advance and the equipment remains on order.
Can collections keep pace with the new space?
APM Terminals is working with the National Port Authority, shipping lines and importers to accelerate container collections and improve cargo movement through the terminal. That work targets dwell directly, while the civil works address where boxes can wait.
For shipowners, charterers and importers, announced capacity is only part of the calculation. The useful measure is whether the 15-16 day range comes down as the relocation, car-park yard and collection programme take effect. Adding yard slots without moving enough boxes simply relocates the queue.
The 2,800 TEU area remains outside current operations, and the 2,312 TEU import area awaits further demolition. APM has land cleared, equipment ordered and partners around the table. The boxes still have to leave.
Monrovia has bought time. It still has to collect the boxes.
via Google News: Ports & Terminals (Source)
More from Amara Osei
Show full bio
Senior reporter covering technology and product news in commercial shipping for industry professionals at Vessels.
160 articles
Linked entries
- Togo to Upgrade 40 km Lomé Port–Adétikopé Rail Line in 2027
- Mexican container traffic rose 2.4%, sharpening the build-or-tune test
- DP World raises Maputo investment to $200m, targets 650,000 TEU
- Posorja terminal expands to 800m berth and 1.4m TEU capacity
- World Bank: terminals at 72.2% utilisation, already past congestion line