Durban container backlog hits 20 days as Navis N4 chaos drags into November
Vessel delays of 14-20 days at Durban Gateway Terminal after the Navis N4 cutover have Metair warning of force majeure, with recovery not expected until February 2027.

Adjustments
- Vessel delays at Durban Gateway Terminal run 14-20 days since the mid-August Navis N4 cutover, with waits of 8.3 days on average in early October.
- Metair's shares fell over 35%; it warned net 2026 costs could rise 20-25% of prior-year EBITDA and said force majeure is possible.
- Transport Minister Barbara Creecy expects the backlog to clear gradually through February 2027, with new equipment due in December.
- Throughput dropped roughly 26-30% after the cutover; ICTSI holds the 49% stake in DGT under a 25-year concession from January 2026.
- Comparisons centre on SPAR's 2023 SAP rollout, which cost an estimated R1.6 billion in lost turnover and R720 million in lost profit.
Vessel delays of 14 to 20 days at Durban Gateway Terminal (DGT), formerly Pier 2, are forcing import-dependent businesses to absorb unrecoverable costs, and automotive supplier Metair has warned it may invoke force majeure. The crisis began after a mid-August cutover to the Navis N4 terminal operating system and has now stretched into November.
Metair, a key supplier to Toyota, Ford, Volkswagen and Isuzu, said the port crisis could push its net 2026 costs up by 20 to 25% of prior-year EBITDA. Its shares plunged more than 35% after the company disclosed that 20-day delays had forced it onto air freight and heavy overtime, temporarily halting one client's production line. CEO Paul O'Flaherty told Moneyweb the group "cannot weather it endlessly" and has no open chequebook for contingency measures as the festive season approaches.
How bad is the backlog?
Transport Minister Barbara Creecy has described the timing of the Navis migration as "not good". After visiting the terminal and counting dozens of ships at anchorage, she said the backlog would take months to clear, with new handling equipment expected in December and gradual recovery through February 2027.
Average vessel waits stood at about 8.3 days in early October. Metair's own figures show they remain severe, with some services reporting berth delays ranging from three days to more than a month. Throughput fell sharply after the cutover — reports cited drops of roughly 26 to 30% versus prior averages — while truck booking systems and yard fluidity also suffered.
DGT and Philippines-based International Container Terminal Services Inc (ICTSI) say Navis N4 has since stabilised and daily moves have returned toward target levels in places. Freight associations call the improvement mere recovery from a depressed base, and the vessel queue hasn't cleared.
What sits behind the concession?
DGT is South Africa's largest container facility and handles a substantial share of the country's port traffic. In January 2026, ICTSI assumed operational control under a 25-year concession in which Transnet retains a 51% stake; ICTSI's investment for the 49% holding was reported at almost R10.5 billion.
The partnership was expected to recapitalise ageing equipment and raise capacity, but the transition exposed deeper weaknesses in equipment reliability, straddle-carrier availability and landside processes. President Cyril Ramaphosa has said government is monitoring the situation until operations are fully restored. Carriers, including COSCO, have adjusted calls, and the episode risks undoing Durban's modest gains in the latest World Bank Container Port Performance Index (CPPI), where it ranked as the most improved but still near the bottom of the global table.
Why SPAR's SAP rollout is the comparison everyone's making
The parallels with SPAR Group's SAP experience are direct. In February 2023, the retailer switched its flagship KwaZulu-Natal distribution centre to SAP S/4HANA. Immediate breakdowns in order picking, dispatch scheduling, inventory visibility and pricing accuracy left stores with empty shelves, eroded retailer loyalty and forced costly workarounds.
SPAR later quantified the damage at R1.6 billion in lost turnover and an estimated R720 million in lost profit. The rollout also prompted governance questions after allegations emerged that three directors had ignored concerns raised in a 2021 whistleblower letter. In 2026, the Giannacopoulos Group, one of SPAR's major franchisees, brought a separate claim of approximately R168.7 million over alleged losses linked to the implementation. Service levels have since improved, but the episode still weighs on performance.
What's the shared lesson?
Both cases follow the same pattern: ambitious system upgrades executed with insufficient buffers, testing or stakeholder communication, then compounded by existing operational constraints. In each instance the KZN logistics node became a chokepoint, costs cascaded to downstream users, and recovery stretched far beyond the original go-live window.
At the port the stakes are national and international — container delays of weeks ripple into automotive production, citrus exports, working-capital strain and higher consumer prices. Industry groups keep pressing for a clear, publicly tracked recovery plan, better equipment reliability and improved truck-appointment systems; DGT is moving toward a new digital platform for the latter.
Metair's warning that meaningful relief may not arrive before the first quarter of 2027 underscores how long "teething" problems can linger. For a port still trying to escape the bottom of global rankings, the Navis experience has become a cautionary parallel to SPAR's SAP saga.
via Google News: Ports & Terminals (Source)
More from Sophie Lindqvist
Show full bio
Market editor covering technology and product news in commercial shipping for industry professionals at Vessels.
163 articles
Linked entries
- Durban truckers stranded as 14-20 day waits hit Gateway Terminal
- Durban Pier 2 delays could stretch to 20 days, KZN business warns
- Transnet Rushes Berth 102 and Rail Relief to Durban Gateway Backlog
- Durban delays reach 20 days as port handles 87.6% of 2025/26 wheat
- Transnet warns ICTSI as Durban vessel delays hit 20 days