Durban Pier 2 delays could stretch to 20 days, KZN business warns
Durban Container Terminal Pier 2 delays could run 20 days, threatening festive-season stock and medication supplies. Transnet denies underinvestment as ICTSI's E-NAVAS system draws blame.

Adjustments
- Pier 2 delays could last up to 20 days; losses on missed Christmas stock could reach hundreds of millions of rand.
- Transnet spent about R1.5 billion on Pier 2 equipment over 18 months, including four ship-to-shore cranes worth R967 million.
- Of 41 urgent pharmaceutical containers identified by the Department of Health, 18 have been delivered; 7 more arrive 23 November–2 December.
- ICTSI took over Pier 2 through the Durban Gateway Terminal partnership on 1 January 2026; Pier 2 handles about 60% of South Africa's container volumes.
- The 2025 World Bank/S&P Global Container Port Performance Index named Durban the most improved port.
By James Calloway
Delays at Durban Container Terminal Pier 2 could run up to 20 days, and KwaZulu-Natal's business community says some cargo stuck on ships may never make the festive-season window. Losses could reach hundreds of millions of rand if Christmas stock misses the sales period.
Andrzej Kiepiela of the KZN Growth Coalition said the business community had been briefed on the situation and called it a serious challenge.
"We have been made aware of the problems and have been told that the delays could last for up to 20 days," Kiepiela said.
What's stuck and what it costs
The concern isn't just tinsel and toys. Some of the stranded cargo is medication. Other consignments are seasonal retail stock that loses most of its value if it misses December.
"This raises serious concerns for the business community because some goods stuck on ships are essential products, such as medication, while others are intended for sale during the Christmas period. If they are not sold during this period, the losses could run into hundreds of millions," Kiepiela said.
He didn't put a precise figure on the exposure. Nobody has. But the scale of the terminal makes the risk concrete: Pier 2 handles roughly 60% of South Africa's container volumes and is Southern Africa's largest and busiest container terminal.
Who's to blame?
Kiepiela pointed the finger at the timing of ICTSI's systems changeover. International Container Terminal Services Inc. operates Pier 2 through the Durban Gateway Terminal partnership, which it took over on 1 January 2026.
"They introduced a new system, and that was when the problems began. They introduced the system at the worst possible time. They should have waited until January or so," he said.
"We have since learnt of claims that there was also no investment in infrastructure at the pier," Kiepiela added.
Reports attribute the delays to repeated breakdowns of container-handling equipment plus capacity constraints tied to the new E-NAVAS truck-booking system, rolled out ahead of the festive-season peak. Note what's missing here: no published throughput figures since the system went live. Everyone is arguing from anecdote and allocation lists.
The timing stings. The 2025 Container Port Performance Index, produced by the World Bank and S&P Global Market Intelligence, had just named Durban the most improved port in the index. That headline now reads awkwardly against 20-day delays at the country's main box gateway.
Transnet pushes back
Transnet rejected claims it failed to invest in the port. In a statement, it said commentary suggesting ICTSI inherited "a broken or wholly run-down operation" through the Durban Gateway Terminal partnership was inconsistent with the evidence.
The state-owned operator listed what Pier 2 received before the handover:
- Four new ship-to-shore cranes, valued at R967 million
- 20 new straddle carriers commissioned
- 40 haulers, 40 trailers, two reach stackers and an empty-container handler
- Broader equipment investment of roughly R1.5 billion over the preceding 18 months
"ICTSI assumed management of Pier 2 after a significant Transnet-funded equipment-renewal programme," the statement said. "The subsequent performance of Durban Gateway Terminal confirms that ICTSI inherited a functioning and productive operating platform."
Fair enough on the hardware list. But cranes and straddles don't explain a truck-booking system choking gate capacity, and Transnet's statement doesn't address E-NAVAS at all.
Pharmaceuticals get priority lanes
On remedial action, Transnet said it is working with Durban Gateway Terminal and making progress moving critical pharmaceutical products through the port system.
The Department of Health supplied a list of pharmaceutical containers requiring urgent evacuation. Of 41 identified containers, 18 have been cleared and delivered to their destinations. Seven more are expected to arrive in South Africa between 23 November and 2 December.
That leaves 16 containers from the urgent list still unaccounted for in the statement. Transnet didn't give a timeline for those.
What to watch
The immediate test is whether the 20-day delay estimate holds or slips. Watch the remaining 16 pharma containers, the December truck-booking slot availability, and whether ICTSI or Transnet publishes throughput data for Pier 2 since the E-NAVAS rollout. Promises of progress are easy. Cleared containers on pharmacies' loading docks are the only metric that counts.
via Google News: Ports & Terminals (Source)
More from James Calloway
Show full bio
Correspondent covering technology and product news in commercial shipping for industry professionals at Vessels.
147 articles
Linked entries
- Transnet warns ICTSI as Durban vessel delays hit 20 days
- Durban truckers stranded as 14-20 day waits hit Gateway Terminal
- Durban Gateway races 20-day backlog with crane repairs and 70-unit fleet order
- Durban delays reach 20 days as port handles 87.6% of 2025/26 wheat
- Durban Port Backlog Triggers KZN Freight Enforcement Push