Durban Gateway races 20-day backlog with crane repairs and 70-unit fleet order
Businesses report 20-day transhipment delays at Durban as DGT deploys OEM repair teams and orders 70 machines through 2028; Transnet prioritises pharma boxes on 16 vessels.
Adjustments
- Durban transhipment delays reaching 20 days amid vessel backlog
- 16 new reach stackers and empty handlers due end-November 2026; 16 RTGs by March 2028
- DGT is 51% Transnet, 49% International Container Services Inc.
- Six of 16 pharmaceutical-carrying vessels completed; seven still approaching SA ports
- Import container dwell time stands at three days, DGT says
Shippers using Durban are waiting up to 20 days for transhipment as Durban Gateway Terminal (DGT) battles a vessel and freight backlog it blames on years of underinvestment in equipment.
DGT, 51% controlled by Transnet and 49% owned by Philippines-based International Container Services Inc., has launched a multi-phase fleet renewal programme combining refurbishment of existing kit with new procurements through 2028.
"While the different actions taken have been necessary, we acknowledge the continued service shortcomings and the unfortunate impact on our clients and partners," the terminal operator said. "All efforts are being undertaken to clear the vessel backlog as soon as possible."
DGT put the root cause squarely on poor and unsafe equipment conditions, the legacy of inadequate maintenance. Original equipment manufacturers are already on site refurbishing ship-to-shore cranes (the quay cranes that work vessels) and straddle carriers, and the operator says availability has steadily improved since that work began.
What equipment is arriving and when?
The renewal timetable runs to March 2028:
- 16 new reach stackers and empty-container handlers by end-November 2026
- 26 second-hand straddle carriers in two batches by end-Q1 2027
- 12 new straddle carriers by Q3 2027
- 16 new rubber-tyred gantry cranes (wheeled yard cranes) in two batches, December 2027 and March 2028
- Additional generators and uninterruptible power supplies to counter grid instability
The terminal's new operating system, NAVIS N4, is now running smoothly and aiding the recovery, DGT said. A new truck appointment system is being implemented, and dwell time for full import containers — discharge to release — currently stands at three days.
On the waterside, DGT is coordinating with Transnet National Ports Authority to secure tugs and pilots, and working with Transnet to offer lines alternative berthing at DCT Pier 1, Maydon Wharf's Berth 102 and Ngqura Container Terminal.
Are pharmaceutical cargoes moving?
Yes, according to Transnet's Friday update. South Africa's Department of Health supplied a list of critical pharmaceutical products on 16 vessels in or approaching South African ports requiring urgent evacuation.
Transnet's tally:
- Six vessels completed, with containers released to destination
- Three vessels due to berth in the following days — one at Pier 1, two at DGT
- Seven vessels still approaching, berths not yet nominated
- A proposal to discharge urgent containers at other terminals under consideration to prevent further queuing in Durban
Transnet said the diversion proposal would be finalised before those vessels arrive, and that it would keep working with the Department of Health, shipping lines and other stakeholders on efficient evacuation of medical supplies.
Is the fix structural or temporary?
Dr Simphiwe Madikizela, senior lecturer at Unisa's Graduate School of Business Leadership, said DGT's problems reach well beyond port operations.
"They have direct implications for international trade, manufacturing, agriculture, employment, investment confidence and the cost of doing business," Madikizela said.
Commenting on Transnet's 19 November 2026 announcement, he welcomed the interventions as necessary but questioned whether they go far enough. He drew a distinction between emergency congestion relief and a sustainable recovery programme restoring the terminal's efficiency.
"Transnet's announcement is a positive development, particularly because it recognises the urgency of the situation and the need for coordinated intervention across the port system. However, I would be cautious about concluding that these measures will be sufficient to resolve the crisis," he said.
The challenge is more than berthing space, he argued. "The fundamental challenge at DGT is a combination of operational inefficiencies, equipment constraints, container-handling capacity, landside congestion and the ability to move cargo efficiently through the terminal," Madikizela said.
"My concern is that some of these interventions may provide temporary relief without necessarily resolving the structural weaknesses that have contributed to the current situation."
via Google News: Ports & Terminals (Source)
More from Sophie Lindqvist
Show full bio
Market editor covering technology and product news in commercial shipping for industry professionals at Vessels.
102 articles
Linked entries
- Transnet adds Berth 102, diverts Durban vessels to Ngqura
- Transnet Rushes Berth 102 and Rail Relief to Durban Gateway Backlog
- Durban truckers stranded as 14-20 day waits hit Gateway Terminal
- Durban Port Backlog Triggers KZN Freight Enforcement Push
- Boluda agrees Samskip deal, targeting 32-vessel short-sea network