Transnet adds Berth 102, diverts Durban vessels to Ngqura
Transnet added Berth 102 for geared vessels, diverted Durban-bound tonnage to Ngqura and returned six STS cranes to Pier 2 by November 21 to ease the terminal backlog.

Adjustments
- Berth 102 at Durban is available immediately for geared vessels and direct discharge
- Sixth STS crane at Pier 2 commissioned 20 November, handed over to operations 21 November
- Durban-bound containers to be discharged at Ngqura and shifted by smaller geared vessels to Berth 102 and the Point terminal
- Cape Town Container Terminal and Cape Town Multi-Purpose Terminal cannot release equipment during peak deciduous fruit export season
- Transnet Freight Rail trains made available to evacuate import containers destined for Gauteng
Transnet has added Berth 102 at Durban for geared vessels and diverted Durban-bound tonnage to Ngqura, with all six ship-to-shore (STS) cranes at Pier 2 operational by November 21.
The state-owned logistics agency is running three measures to clear the backlog at the Durban Gateway Terminal (DGT), the container terminal it operates at the Port of Durban:
- Berth 102, added to accommodate geared vessels (ships with their own cargo cranes) for direct discharge.
- Divertion of vessels to the Ngqura Container Terminal (NCT) in the Eastern Cape.
- Additional STS cranes to lift terminal capacity.
Under the diversion, Durban-bound containers can be discharged at NCT and then transferred by smaller geared vessels to Berth 102 and the Point terminal. Transnet Port Terminals (TPT) and operator DGT are coordinating the identification of suitable vessels for that routing, and Transnet says Berth 102 reinforces the intervention. The berth is available immediately, and shipping lines are encouraged to take up the additional capacity rather than wait for the crane programme to finish.
What do the returned cranes change?
The cranes moved back to Pier 2 after a long-term refurbishment at TPT's Pier 1, and Transnet says they will raise terminal capacity and support a reduction in the Durban vessel backlog. The final STS crane is due for commissioning on November 20 and handover to operations on November 21, by which time all six cranes will be working.
Can other terminals release equipment?
TPT has reviewed equipment across the business that could move to DGT. Only two terminals operate similar equipment, the Cape Town Container Terminal (CCT) and the Cape Town Multi-Purpose Terminal (CMPT), and neither can release any of it: both are in the peak deciduous fruit export season and require the capacity they hold. TPT says it will keep assessing opportunities to optimise equipment deployment across its network as operational conditions evolve.
Why rail is part of the answer
The landside is being cleared with rail as well as quay cranes. Transnet Freight Rail (TFR) has made trains available to evacuate import containers destined for Gauteng, and Transnet is encouraging the industry to use them to support the urgent evacuation and decongestion of the landside. The agency is also prioritising essential cargo, including pharmaceuticals and automotive parts, ahead of other volumes so that priority boxes leave the terminal first.
“Resolving the backlog will require sustained execution and close coordination between terminal operations, Transnet National Ports Authority, TFR, shipping lines, customers and other stakeholders across the port system,” Transnet says.
The congestion has hit shipping lines, cargo owners, customers and the broader logistics value chain, Transnet says, and the interventions are coordinated and monitored at senior leadership level. Stated objectives are to increase available capacity, improve vessel evacuation, progressively reduce the backlogs and restore operational fluidity, with regular updates to critical stakeholders as the work progresses. Transnet says it will work with all stakeholders to restore operational performance as quickly and sustainably as possible.
No backlog tonnage or clearance date has been published, leaving the November 21 crane handover as the only fixed milestone in the plan.
via Google News: Ports & Terminals (Source)
More from Rebecca Stone
Show full bio
News editor covering people, launches and day-to-day practice in commercial shipping for industry professionals at Vessels.
59 articles
Linked entries
- Transnet Rushes Berth 102 and Rail Relief to Durban Gateway Backlog
- Conakry Hits 11.5 Days Waiting as Global Port Congestion Deepens
- Savannah handles 565,366 TEU as Panama raises daily transits
- Boluda agrees Samskip deal, targeting 32-vessel short-sea network
- Port of Savannah lifts October 2026 volume 25% to 565,366 TEU