Rijeka picks Končar for 17.5 MW shore power at two terminals
Rijeka's port authority picked Končar to build 17.5 MW of shore power at Adriatic Gate and Rijeka Gateway, serving two vessels at once ahead of FuelEU Maritime's 2030 rule.

Adjustments
- Port of Rijeka Authority selected Croatian firm Končar to design and build the OPS system at both container terminals
- Adriatic Gate Container Terminal at Brajdica: 10 MW planned capacity; Rijeka Gateway at Zagreb Deep Sea Container Terminal: 7.5 MW
- Combined 17.5 MW capacity enables two vessels to be supplied with shore-side electricity simultaneously
- Two-year development schedule, with dedicated substations and cable management at both terminals, co-financed by the EU's Connecting Europe Facility
- FuelEU Maritime requires ships above 5,000 gross tonnage to plug in from 1 January 2030 at TEN-T ports, with an exemption for stays under two hours
By Rebecca Stone
17.5 MW across two container terminals. The Port of Rijeka Authority has selected Croatian firm Končar to design and build an onshore power supply (OPS) system at both container terminals in the port, with a combined planned capacity of 17.5 MW and enough capacity to supply two vessels with shore-side electricity at the same time.
Rijeka's build-out will let ships take electricity from the shore instead of burning fuel to generate power onboard, cutting air pollutants, emissions and noise while they sit at berth.
What does the Končar contract cover?
- Design and build of the OPS system by Končar, selected by the Port of Rijeka Authority
- Adriatic Gate Container Terminal, Brajdica: 10 MW planned capacity
- Rijeka Gateway, at the Zagreb Deep Sea Container Terminal: 7.5 MW capacity
- Dedicated substations at both terminals
- A cable management system for the vessel connections
- Simultaneous shore-side supply to two vessels
- Development over the next two years
- Co-financing from the EU's Connecting Europe Facility (CEF)
Adriatic Gate's planned 10 MW runs 2.5 MW above Rijeka Gateway's 7.5 MW, making the Brajdica installation the larger of the two. The award covers design and build at both sites, so the port's two container terminals come onto the grid within one programme rather than one berth at a time.
How long will the build take, and who funds it?
Končar will develop the system at the port over the next two years. Dedicated substations go in at both terminals, and a cable management system will handle the vessel-side connections.
The project draws co-financing from the EU's Connecting Europe Facility. The two-year programme places delivery inside the window that ends with the 1 January 2030 FuelEU Maritime requirement, which turns shore power from an emissions measure into a compliance obligation for the ships that call.
What changes on 1 January 2030?
From 1 January 2030, FuelEU Maritime requires container ships and passenger ships above 5,000 gross tonnage (a measure of enclosed volume, not weight) to plug into shore power and use it for all their electricity needs while moored at the quay.
The rule covers EU ports on the trans-European transport network (TEN-T) that receive regular calls from those ships, and exempts vessels that stay less than two hours. Calls of two hours or more sit inside the obligation, which puts the two-vessel capability at Rijeka against the calls that must plug in.
Rijeka covers both of its container terminals with a single award, so a plugging-in call at Brajdica or at the Zagreb Deep Sea Container Terminal carries the same requirement.
Which European ports are moving first?
Many ports across Europe have started deploying shore power. Valencia port launched a tender last month for a new electrical substation, to strengthen power supply at the port and support the rollout of OPS systems for vessels.
In January, a Port of Rotterdam venture selected Swiss technology firm ABB to build shore power infrastructure across three deep-sea container terminals, with operations scheduled to begin in the second half of 2028.
Rotterdam's ABB award spans three deep-sea container terminals against Rijeka's two, and both programmes sit ahead of the 2030 compliance date. For carriers, the practical difference is the network behind the plug: a call at Brajdica or at the Zagreb Deep Sea Container Terminal draws on 17.5 MW of dedicated capacity, with two vessels served at once.
For Rijeka, the arithmetic is fixed: 17.5 MW, two container berths, two vessels supplied simultaneously, and a compliance date of 1 January 2030.
via Google News: Ports & Terminals (Source)
More from Rebecca Stone
Show full bio
News editor covering people, launches and day-to-day practice in commercial shipping for industry professionals at Vessels.
31 articles
Linked entries
- Three bidders vie for Rs 117.33bn VOC marine package
- Boskalis-Van Oord-Rohde Nielsen JV wins Gothenburg fairway deepening
- Gothenburg Awards Fairway Dredging Contract for Mega-Boxship Access
- DEME orders two uncrewed offshore survey vessels for 2027
- World Bank: terminals at 72.2% utilisation, already past congestion line