Vessels Queue 20 Days Off Durban as ICTSI Concession Stalls
Durban container ships wait up to 20 days for berths after ICTSI's 25-year Pier 2 concession faltered; Metair warns of force majeure and 20-25% earnings hit.

Adjustments
- Container vessels wait up to 20 days for berths outside Durban harbour
- Metair expects full-year earnings to drop 20-25 percent and may declare force majeure
- TNPA gave ICTSI a three-month ultimatum to hit performance benchmarks
- ICTSI operates Pier 2 under a 25-year joint venture concession
- Durban handles more than half of South Africa's container traffic
Container ships are anchoring off Durban for up to 20 days waiting for berths, months after the Philippines' ICTSI took over the port's flagship container terminal under a 25-year concession (a long-term operating contract granted by the port authority).
The delays have pushed Metair, an automotive components supplier to Toyota, Ford and Isuzu assembly lines, to warn it may declare force majeure (a contractual escape clause for events outside a party's control). The group expects full-year earnings to fall 20 to 25 percent. Importers of pharmaceuticals and medical supplies have flagged stockouts, and fresh produce exporters are rerouting perishable cargo at steep logistical cost.
Durban handles more than half of South Africa's container traffic, so when the node seizes, the domestic supply chain stalls from factory floor to retail shelf.
What went wrong at Pier 2?
The terminal, rebranded Durban Gateway Terminal, was handed to International Container Terminal Services Inc., the Manila-based operator controlled by billionaire Enrique Razon. Transnet selected ICTSI as preferred joint venture partner to inject capital, run day-to-day operations and lift the facility out of global bottom-tier efficiency rankings.
Transport Minister Barbara Creecy pitched the deal as a clean break from Transnet's chronic dysfunction. Instead, the transition has brought software integration issues and operational paralysis during peak shipping volumes. The concession hasn't resolved the underlying decay — it's shifted the liability from public balance sheets to private press releases.
Who is to blame — operator or state?
Both sides are trading accusations. Creecy confirmed the Transnet National Ports Authority has issued ICTSI a three-month ultimatum: hit performance benchmarks or face licence cancellation.
ICTSI has hit back directly at the state freight monopoly. The operator says it inherited an operational graveyard — decrepit, unsafe machinery, broken straddle carriers (the gantry vehicles that shuttle containers across the yard) and neglected ship-to-shore cranes, all products of years of Transnet under-investment and deferred maintenance. ICTSI is now sourcing second-hand straddle carriers and patching decades-old gear to clear yard congestion.
The dispute exposes a basic structural reality: a concession can't repair machines run into the ground over a decade. Transferring terminal management without a fully funded overhaul of the physical infrastructure delivers the same paralysis under private management.
What is the emergency fix?
Transnet has opened a single auxiliary berth at Pier 1 for geared vessels (ships with their own cargo-handling cranes) and diverted traffic to Ngqura near Gqeberha. Moving stranded containers back to KwaZulu-Natal by rail and feeder ships adds freight costs that South African producers and consumers ultimately carry.
Threatening to revoke ICTSI's licence within 90 days buys political cover, but it doesn't solve the problem at the quayside. South Africa's industrial competitiveness depends on efficient, sovereign logistics arteries, and handing critical national infrastructure to an offshore contractor without fixing the basic tools of the trade has simply privatised the backlog.
via Google News: Ports & Terminals (Source)
More from Sophie Lindqvist
Show full bio
Market editor covering technology and product news in commercial shipping for industry professionals at Vessels.
185 articles
Linked entries
- Durban backlog to run into 2027 as Transnet warns of three-year recovery
- Transnet warns ICTSI as Durban vessel delays hit 20 days
- Transnet Rushes Berth 102 and Rail Relief to Durban Gateway Backlog
- Durban Gateway races 20-day backlog with crane repairs and 70-unit fleet order
- Durban container backlog hits 20 days as Navis N4 chaos drags into November