Durban backlog to run into 2027 as Transnet warns of three-year recovery

Transnet warns Durban congestion will last until January 2027, with 10-11 vessels queuing daily after ICTSI's Navis N4 migration cut container processing by up to 30%.

South Africa’s port crisis deepens as Durban backlog threatens 2027 operations - Bona Magazine
Exhibit · South Africa’s port crisis deepens as Durban backlog threatens 2027 operations - Bona Magazine — Julius_Silver / pixabay

Adjustments

  1. Durban backlog expected to persist until January 2027, with full capacity recovery taking up to three years
  2. Durban Gateway Terminal faces a backlog of 10-11 vessels daily, with berthing waits of up to 10 days
  3. Navis N4 system migration in August cut container processing by as much as 30%
  4. Emergency measures include vessel diversions to Ngqura, extra berthing at Pier 1, and added rail capacity to Gauteng
  5. ICTSI is bringing in new ship-to-shore cranes; first upgrade phase completes within 18 months

Durban will not clear its container backlog until January 2027 at the earliest, and Transnet says the port may need up to three years to return to full operational capacity. The number lands as the Durban Gateway Terminal, run by Philippines-based International Container Terminal Services Inc. (ICTSI), still works through roughly 10 to 11 delayed vessels a day, with ships waiting up to 10 days before berthing.

Transnet group chief operating officer Solly Letsoalo said the terminal has improved since August, but the peak festive season will keep the queue alive through December. "Things have gotten better if I compare to where we were in August …but it won't take us out of the backlog in December. But probably come January — because the peak also would have gone down — we will see a drop in the backlog," Letsoalo told Business Day.

What triggered the pile-up?

The congestion intensified in August after the introduction of a new Navis N4 terminal operating system (the software that schedules and tracks container moves) at the Gateway Terminal. Container processing declined by as much as 30% within days of the migration, MyBroadband reported. Trucking companies hit registration difficulties and long queues at the gates.

The ripple effects are now showing up across the economy. Essential imports — pharmaceuticals, automotive components and retail merchandise — are moving slowly, raising fears of supply shortages and delivery delays during the festive trading season.

Which sectors are taking the hit?

The citrus trade is one visible casualty. The Citrus Growers' Association of Southern Africa attributed missed international market supply windows to the logistics backlogs, contributing to a weaker-than-expected 2026 export season.

Retailer Pepkor has warned that port operational problems and delayed stock deliveries could undermine festive-season sales — a serious concern for a chain that depends on fast inventory turns through the December peak.

What are the emergency interventions?

The government and Transnet have rolled out a package of measures, reported by Moneyweb, to shift cargo away from the choked terminal:

  • Diverting some vessels to the Port of Ngqura in Gqeberha
  • Making additional berthing capacity available at Pier 1
  • Increasing rail capacity to move imported containers destined for Gauteng
  • Prioritising essential cargo — particularly medicines and automotive components — before vessel berthing

Transnet spelled out the last point in a statement carried by SAnews: "We are also prioritising all essential cargo (pharmaceuticals, auto parts, etc.) before vessel berthing to ensure priority evacuation from the terminal."

The diversions matter for operators still calling South Africa. Ngqura, a deep-water container port east of Gqeberha, is absorbing traffic that would normally berth in Durban, while the added rail capacity targets the Durban-to-Gauteng corridor — the main inland leg for imported consumer goods.

What is ICTSI doing about it?

Equipment is the medium-term fix. Letsoalo said ICTSI is bringing in additional hardware, including new ship-to-shore cranes, alongside infrastructure improvements designed to accommodate more efficient rubber-tyred gantry cranes (the wheeled yard cranes that stack containers between the quay and the gate).

The first phase of the upgrades should be complete within 18 months, according to Letsoalo. Full operational recovery, however, could take up to three years — a timeline that stretches well beyond the current 2027 backlog clearance estimate for overall capacity restoration.

Does this raise questions about port reform?

The crisis has renewed scrutiny of South Africa's port reform programme and whether private-sector participation will deliver the operational improvements the country's logistics network needs. ICTSI's takeover of the Gateway Terminal was itself part of that private participation push, and the Navis N4 migration that triggered the slowdown happened on the new operator's watch.

For charterers and operators, the practical read is straightforward. Expect berth waits of up to 10 days at Durban into December, plan diversions through Ngqura if schedules allow, and treat the January 2027 backlog clearance as a floor, not a ceiling, on recovery. With three years cited for full capacity, South Africa's premier container gateway will remain a planning risk for some time.

via Google News: Ports & Terminals (Source)

Share this article:

More from Tom Whitfield

Tom Whitfield

Show full bio

Staff writer covering companies, deals and strategy in commercial shipping for industry professionals at Vessels.

192 articles

Linked entries

  1. Durban truckers stranded as 14-20 day waits hit Gateway Terminal
  2. Durban delays reach 20 days as port handles 87.6% of 2025/26 wheat
  3. Durban Gateway races 20-day backlog with crane repairs and 70-unit fleet order
  4. Durban congestion costs shippers R17,500 per container per day