Colombo's East Container Terminal to start partial operations this month
Colombo's ECT begins partial operations this month at limited capacity, with 15 straddle carriers due in September 2027 and full capacity targeted for mid-2028.

Adjustments
- ECT begins partial operations by end of November 2026
- First batch of 15 straddle carriers due around September 2027; terminal to reach 50% capacity then
- Full capacity scheduled for Q1 2028, with full utilisation targeted mid-2028
- Project hit only 10% completion by the original 2024 deadline; now around 90% complete
- 85% of Colombo's cargo is transhipment traffic controlled by about 10 major shipping lines
Colombo Port's East Container Terminal (ECT) will begin partial operations by the end of November 2026, after testing wraps up, Sri Lanka's Deputy Minister of Ports and Civil Aviation Janitha Ruwan Kodithuwakku has confirmed.
Capacity will be limited at first. The Sri Lanka Ports Authority (SLPA) is still waiting on straddle carriers, the gantry-style vehicles that shuttle containers between quay and stack. Kodithuwakku told local media the first batch of 15 carriers should arrive around September 2027. By then, the infrastructure needed to run the terminal at 50% capacity should be in place.
What is the build-out timeline?
The procurement plan runs in stages:
- September 2027: first 15 straddle carriers arrive; 50% capacity infrastructure ready
- Four months later: procurement of a further 15 carriers completed
- Q1 2028: facilities for full capacity in place
- Mid-2028: target for full operational capacity, backed by a parallel marketing programme
Why did the project slip?
Construction started in 2022, with completion originally scheduled for 2024. Only around 10% of the work was done by that deadline. Government intervention pushed through another 60%, taking overall progress to roughly 90% by 2026.
To avoid the delays that dog conventional state-sector operations, the Government is establishing a new company wholly owned by the SLPA to manage the terminal. Talks continue on possible private-sector involvement in future operations. Kodithuwakku said no decision had been taken on sharing ownership, adding that the Government wants a management structure capable of competing with other terminals while generating the highest possible returns for the Ports Authority.
One constraint shapes that debate. Kodithuwakku noted the SLPA has already financed the entire ECT project, so no additional capital investment is required. The immediate priority, he said, is an effective marketing strategy to attract shipping business.
Why transhipment matters here
Around 85% of cargo handled at the Port of Colombo is transhipment traffic, largely controlled by approximately 10 major international shipping lines. Winning a share of that business is the terminal's commercial battleground, and Kodithuwakku made clear that marketing, not fresh capex, will decide the outcome.
What about the 2020 union protests?
Trade unions, including those affiliated with the National People's Power (NPP), protested in 2020 against a proposed private-sector partnership. Kodithuwakku said those objections targeted earlier ownership arrangements which, in his view, were designed to conceal inefficiencies in state-sector management. He stressed the ECT has remained under the SLPA in keeping with the Government's commitment.
What happens next?
The SLPA will manage the terminal initially while the authorities evaluate whether continued full state ownership and operation, or an alternative management arrangement, delivers the greatest benefit to the country and the Ports Authority. Kodithuwakku reiterated the terminal needs no further investment at this stage, because the Ports Authority has already completed the funding process. Attracting business through a strong marketing approach, he said, is now essential.
via Google News: Ports & Terminals (Source)
More from Tom Whitfield
Show full bio
Staff writer covering companies, deals and strategy in commercial shipping for industry professionals at Vessels.
165 articles
Linked entries
- Chennai woos Taiwanese carriers with $1.88bn terminal pitch
- India Clears 2 M TEU Second Container Terminal at Kamarajar Port
- Cabinet approves 2m TEU Kamarajar terminal in Rs 4,288 crore PPP
- Durban Gateway races 20-day backlog with crane repairs and 70-unit fleet order
- India approves ₹4,288.26 crore Kamarajar terminal for 2 million TEU