Cabinet approves 2m TEU Kamarajar terminal in Rs 4,288 crore PPP
India’s Cabinet approved a Rs 4,288.26 crore, 2.0 million TEU terminal at Kamarajar Port for Chennai-Ennore trade, split across two phases and a 40-year DBFOT concession.

Adjustments
- The second terminal carries an estimated project cost of Rs 4,288.26 crore and 2.0 million TEU of annual capacity.
- Phase I covers 1.1 million TEU at Rs 2,429.32 crore; Phase II covers 0.9 million TEU at Rs 1,858.94 crore.
- The 40-year DBFOT concession includes 48 months of construction, with full commercial operations scheduled for month 49.
- KPL handled 49.08 million tonnes and 1,008 vessels in FY 2025-26, while its existing terminal ran at about 88 per cent utilisation.
- KPL will fund an estimated Rs 450 crore dredging programme; the concessionaire will arrange the required project financing.
Rs 4,288.26 crore is the estimated project cost for a second container terminal at Kamarajar Port Limited (KPL), with 2.0 million TEU of annual handling capacity. India’s Union Cabinet, chaired by Prime Minister Narendra Modi, approved the proposal on Wednesday under a public-private partnership on a design, build, finance, operate and transfer (DBFOT) basis.
The arithmetic, at least, is not timid.
The plan covers a 900-metre-long terminal with an 18-metre design draft and a 30-metre berth width. It can accommodate vessels of up to 24,346 TEU and 400 metres overall. The design targets larger mainline vessels and stronger connectivity with international shipping routes. For owners and charterers, that is the commercial point; the rest is project plumbing.
What do the two phases cost?
The Rs 4,288.26 crore estimated PPP project cost includes GST and divides into two work packages:
- Phase I: Rs 2,429.32 crore and 1.1 million TEU of annual capacity.
- Phase II: Rs 1,858.94 crore and 0.9 million TEU of annual capacity.
KPL will separately bear an estimated Rs 450 crore for dredging, according to the official statement. The selected concessionaire must arrange the required financing and recover its investment through user charges under the Concession Agreement and applicable tariff framework. Bids will run through a transparent, open global process.
When does capacity arrive?
The concession runs for 40 years, including 48 months for construction. Phase I must be complete within 24 months from the Date of Award of Concession, with commercial operations starting in the 25th month. Phase II construction runs from month 25 through month 48, followed by full commercial operations in month 49.
A 48-month construction schedule for a 2.0 million TEU build is brisk. Full operations, however, sit in month 49.
How close is the existing terminal to full?
KPL handled 49.08 million tonnes of cargo and 1,008 vessels in FY 2025-26, including more than 7 lakh TEUs of container traffic. Its existing container terminal has installed capacity of 0.8 million TEU per year and handled about 0.7 million TEU in FY 2025-26, equal to utilisation of roughly 88 per cent.
India’s container traffic grew at about a 7 per cent compound annual growth rate over the past five years, while KPL’s container traffic rose approximately 9.9 per cent over the same period. A feasibility study projects continued growth in the south-eastern region, supporting the decision to add capacity at KPL.
Which cargo will fill the boxes?
The terminal is intended to meet growing containerised export-import demand from the Chennai-Ennore industrial and economic region and the wider southern hinterland. The proposal identifies five cargo groups:
- Automobiles and auto components
- Engineering goods
- Electronics
- Chemicals
- Other manufactured products
The project aligns with Maritime India Vision 2030 and Maritime Amrit Kaal Vision 2047. The official statement expects it to strengthen KPL as a container gateway on India’s East Coast, improve the efficiency of the maritime logistics chain and support EXIM trade.
For shipping lines, the test arrives in month 49. Capacity is easy to announce; calls still have to follow.
via Google News: Ports & Terminals (Source)
More from Amara Osei
Show full bio
Senior reporter covering technology and product news in commercial shipping for industry professionals at Vessels.
185 articles
Linked entries
- India Clears 2 M TEU Second Container Terminal at Kamarajar Port
- India approves ₹4,288.26 crore Kamarajar terminal for 2 million TEU
- Chennai woos Taiwanese carriers with $1.88bn terminal pitch
- Three bidders vie for Rs 117.33bn VOC marine package
- JNPA Hands 8-Year Nhava Sheva Rail Yard Contract to Gateway Distriparks