India approves ₹4,288.26 crore Kamarajar terminal for 2 million TEU
India has approved a ₹4,288.26 crore, 2 million TEU second terminal at Kamarajar Port, with 1.1 million TEU due in phase one and a 40-year PPP concession.
Adjustments
- CCEA approved the project on 25 November 2026.
- The terminal will add 2 million TEU of annual handling capacity.
- Estimated project cost is ₹4,288.26 crore including GST; KPL estimates ₹450 crore for dredging.
- The concession runs for 40 years, including 48 months of construction.
- Phase one opens in month 25 with 1.1 million TEU; full operations start in month 49.
India’s Union Cabinet approved a ₹4,288.26 crore second container terminal at Kamarajar Port Limited (KPL) in Tamil Nadu on 25 November 2026, adding annual handling capacity for 2 million twenty-foot equivalent units (TEU).
The Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi, cleared the project in New Delhi. KPL will execute it through a public-private partnership (PPP) under a design, build, finance, operate and transfer (DBFOT) model, with the selected operator responsible for financing construction.
What will the new berth handle?
The terminal will measure 900 metres in length, with a berth width of 30 metres and a design draft of 18 metres. The two-stage programme will deliver 1.1 million TEU of annual capacity in phase one and 0.9 million TEU in phase two, reaching the full 2 million TEU when operations start in month 49.
At full scale, the berth can accommodate ships up to 400 metres long carrying as many as 24,346 TEU. That combination should improve direct shipping connectivity. It could also reduce reliance on overseas transshipment hubs and associated feeder transportation costs.
How is the project financed?
The estimated expenditure includes goods and services tax (GST), with ₹2,429.32 crore allocated to phase one and ₹1,858.94 crore to phase two, while the selected private concessionaire will arrange the full project investment.
KPL will separately spend an estimated ₹450 crore on dredging. The 40-year concession includes the 48-month construction programme.
Open global bidding will select the concessionaire. It will recover its investment through user charges under the applicable tariff framework and concession agreement.
The delivery schedule runs as follows:
- First-phase construction: Within 24 months after the concession award.
- First-phase operations: From month 25, with 1.1 million TEU of annual capacity.
- Second-phase construction: Between months 25 and 48.
- Full-scale operations: From month 49, with 2 million TEU of annual capacity.
“There will be no direct financial implication for the Centre towards the PPP component,” the government said. The concessionaire remains responsible for arranging the required investment.
Why is Kamarajar expanding now?
Kamarajar handled 49.08 million tonnes of cargo and 1,008 vessels during financial year 2025-26, while container traffic crossed 7 lakh TEU over the same period.
The existing container terminal has 0.8 million TEU of installed annual capacity. It handled around 0.7 million TEU at approximately 88 per cent utilisation.
Port container traffic grew by about 9.9 per cent annually over five years, against roughly 7 per cent growth nationally, prompting the expansion as export-import volumes rose. The project also responds to demand from the Chennai-Ennore industrial belt and manufacturing centres across southern India.
Which cargo will use the terminal?
The terminal will serve cargo from Tamil Nadu, Karnataka, Andhra Pradesh, Telangana and neighbouring regions, with automobile manufacturing, auto components, engineering, electronics, chemicals and other industrial sectors among the expected beneficiaries.
About 750 direct and indirect employment opportunities will arise during construction. Around 800 additional opportunities are expected once the terminal becomes operational.
Who owns the port, and how large is it?
Kamarajar Port sits on Tamil Nadu’s eastern coastline near the Chennai industrial region. It handles petroleum products, coal, liquefied natural gas (LNG), liquefied petroleum gas (LPG), automobiles, containers and general cargo.
Formerly Ennore Port Limited, it is one of India’s 12 major ports. Chennai Port Authority owns it outright under the Ministry of Ports, Shipping and Waterways.
In financial year 2025-26, Kamarajar generated approximately ₹1,280 crore in revenue. Profit before tax (PBT) stood at ₹924 crore. Cargo volume recorded a 13.64 per cent compound annual growth rate over the preceding five years.
What changes for ship and cargo owners?
The 18-metre design draft and 400-metre vessel limit should support direct calls by large mainline container ships on international liner services, potentially reducing reliance on overseas transshipment hubs and associated feeder transportation costs.
Alignment with Maritime India Vision 2030 and Maritime Amrit Kaal Vision 2047 links the project to India’s wider goals for stronger port infrastructure, better logistics efficiency and a larger role in global shipping networks.
Full operations should strengthen Kamarajar’s role in international maritime trade, support southern industrial growth and improve India’s competitiveness, according to the government’s stated project rationale.
via Google News: Ports & Terminals (Source)
More from Tom Whitfield
Show full bio
Staff writer covering companies, deals and strategy in commercial shipping for industry professionals at Vessels.
156 articles
Linked entries
- India Clears 2 M TEU Second Container Terminal at Kamarajar Port
- Cabinet approves 2m TEU Kamarajar terminal in Rs 4,288 crore PPP
- Chennai woos Taiwanese carriers with $1.88bn terminal pitch
- JNPA Hands 8-Year Nhava Sheva Rail Yard Contract to Gateway Distriparks
- Gateway Distriparks wins eight-year JNPA common rail yard mandate