CMAL Takes Delivery of Delayed Islay Ferry MV Loch Indaal in Turkey
CMAL has accepted delivery of the 5,861-ton MV Loch Indaal from Turkey's Cemre yard, about 20 months late. The battery-hybrid ferry will carry 450 passengers and 107 vehicles on CalMac's Islay route.

Adjustments
- MV Loch Indaal is a 5,861-ton ferry delivered by Cemre Marin Endustri AS, Yalova, Turkey
- Construction ran approximately 20 months behind schedule
- Capacity: 450 passengers and 107 vehicles on the Islay–Kennacraig route
- It is the second of four newbuilds; two larger 6,120-ton ferries will serve the Outer Hebrides
- Propulsion is diesel-electric battery-hybrid; vessel is certified and awaiting delivery voyage
Caledonian Maritime Assets Limited (CMAL), the state-backed owner of Scotland's ferry fleet, ports and harbours, has formally accepted delivery of the MV Loch Indaal, a 5,861-ton newbuild constructed at Cemre Marin Endustri AS in Yalova, Turkey. The vessel is the second of four ferries completed so far under the programme at the Eastern European yard.
The handover closes a construction chapter that ran roughly 20 months late. The ferry is now preparing for its repositioning voyage from Turkey to Scotland, where it will undergo crew familiarisation and operational trials before entering revenue service.
What capacity does the new ferry add?
The diesel-electric battery-hybrid-powered Loch Indaal will accommodate 450 passengers and 107 vehicles once it enters service. It joins its sister ship, the MV Isle of Islay, on CalMac's route linking Islay with Kennacraig on the Kintyre peninsula on the Scottish mainland.
CalMac chief executive Kevin Hobbs called the delivery a "significant step forward" for the operator, which runs the extensive west coast network serving Scotland's islands.
Where do the remaining newbuilds fit?
The two larger vessels still to come from the Turkish yard, each of 6,120 tons, are destined for the Outer Hebrides. They will operate the Uig (Skye) links to Tarbet on North Uist and to Lochmaddy on Lewis and Harris, reinforcing lifeline connections across the Minch.
The Loch Indaal has already received its required certifications at the shipyard, clearing the administrative path for the delivery voyage. Certification, familiarisation and operational trials remain the gating steps before the ferry carries its first fare-paying passengers and vehicles on the Islay run.
The programme's pace has drawn sustained scrutiny, given that this delivery alone absorbed around 20 months of delay. For island communities and freight operators dependent on the Islay corridor, the added capacity — a second large vessel alongside the Isle of Islay — will relieve one of the network's most heavily utilised crossings.
Attention now shifts to the 6,120-ton pair, whose delivery timing will determine whether the Outer Hebrides links see relief on a comparable schedule.
The Loch Indaal should enter service once trials conclude in Scotland.
via Google News: Shipbuilding (Source)
More from Rebecca Stone
Show full bio
News editor covering people, launches and day-to-day practice in commercial shipping for industry professionals at Vessels.
93 articles
Linked entries
- CMAL takes delivery of Loch Indaal, 20 months late
- CMAL warns direct ferry awards to Ferguson Marine are 'folly'
- CMAL warns it would be 'folly' to give Ferguson Marine new ferry contracts
- Seaway 7 lines up Alfa Lift trio for 1.4GW Berwick Bank B
- ABB wins order to power third WSF hybrid-electric ferry newbuild