Seaway 7 lines up Alfa Lift trio for 1.4GW Berwick Bank B
Seaway 7 will deploy Alfa Lift, Strashnov and Phoenix on SSE's 1.4GW Berwick Bank B, with offshore work pencilled in for 2029-30 pending SSE's late-2027 FID.

Adjustments
- Seaway 7 names Alfa Lift, Strashnov and Phoenix for 1.4GW Berwick Bank B; offshore work 2029-2030.
- Scope covers ~90 fixed-bottom foundations plus inter-array cables in ~52 m average depth.
- SSE expects the world's deepest fixed-bottom wind farm; part of 4.1GW Berwick Bank complex.
- FID expected late 2027; construction could start 2028 and run into 2031.
- Seaway 7 previously delivered Beatrice and Seagreen for SSE.
Seaway 7 has named three vessels for SSE Renewables' 1.4GW Berwick Bank B offshore wind project off Scotland. Offshore work would run in 2029 and 2030 — if the contract survives final award.
The installation fleet comprises the Seaway Alfa Lift, the Seaway Strashnov and the Seaway Phoenix. All three belong to the Subsea 7 subsidiary's proposed engineering, procurement, construction and installation package covering turbine foundations and inter-array cables.
SSE picked Seaway 7 as preferred supplier in October. The scope includes design, supply and installation of roughly 90 fixed-bottom turbine foundations.
Where does the work actually happen?
The site sits around 38 km off the Scottish Borders, in the outer Firth of Forth. Average water depth runs at roughly 52 m. That figure matters: SSE expects Berwick Bank B to become the world's deepest fixed-bottom offshore wind farm once completed.
Berwick Bank B forms part of the wider Berwick Bank complex, which carries a proposed capacity of approximately 4.1GW.
What could still stop it?
Plenty. The agreement remains subject to final contract award and SSE's final investment decision, expected in late 2027. So the vessel lineup is a plan, not a commitment, and a 2027 FID leaves two years for economics to move against the project.
Subject to approval, the timeline looks like this:
- Preparatory offshore construction from 2028
- Foundation and cable installation continuing into 2031
- Main offshore campaign in 2029 and 2030
That's a long runway for a contract that hasn't been signed.
Does the partnership have form?
Yes. Seaway 7 previously worked with SSE on the Beatrice and Seagreen offshore wind farms. That track record explains the preferred-supplier status, though it doesn't shorten the FID wait.
For owners watching the installation market, three heavy-lift vessels committed to a single Scottish project across 2029-2030 tightens availability in the North Sea window. But nothing is locked until SSE signs — and late 2027 is a long way off.
via Splash 247 (Source)
More from James Calloway
Show full bio
Correspondent covering technology and product news in commercial shipping for industry professionals at Vessels.
109 articles
Linked entries
- Port of Blyth unveils 3-hectare plan and 1m channel deepening
- CMAL Takes Delivery of Delayed Islay Ferry MV Loch Indaal in Turkey
- Boskalis-Van Oord-Rohde Nielsen JV wins Gothenburg fairway deepening
- CMAL takes delivery of Loch Indaal, 20 months late
- Hatenboer-Water doubles testing capacity with Schiedam rebuild