Cemre delivers Loch Indaal ferry to CMAL 20 months late
Cemre Shipyard has handed over the 95m diesel-electric Loch Indaal to CMAL, 20 months late. The £200m four-ferry order still carries slips into 2027, and Glen Rosa is eight years behind.

Adjustments
- Loch Indaal was delivered 20 months after its February 2025 contractual date; the diesel-electric ferry is 95m long.
- Loch Indaal carries 450 passengers and either 100 passenger cars or 14 commercial vehicles.
- Four ferries were contracted in two 2022 and two 2023 agreements worth approximately £200m.
- CMAL covered an extra £20m in shipbuilding costs and paid £23m in June 2026 to assume ownership of three unfinished ferries.
- Lochmor and Claymore are scheduled for Q2 2027, while LNG dual-fuel ferry Glen Rosa is eight years behind schedule.
By Amara Osei
Turkey’s Cemre Shipyard delivered the 95-metre Loch Indaal to Scottish maritime asset manager Caledonian Maritime Assets Limited (CMAL) 20 months after the February 2025 contractual date. The yard has cleared one vessel; the wider programme has not cleared its timetable.
What does the delayed handover mean for CMAL?
The diesel-electric ferry can carry 450 passengers and either 100 passenger cars or 14 commercial vehicles. It has certification from the UK Maritime and Coastguard Agency (MCA) and Lloyd’s Register (LR). The vessel is now complete. The order behind it is another matter.
CMAL and Cemre signed contracts for four diesel-electric passenger/ro-ro ferries, with two agreements in 2022 and two in 2023. The package was worth approximately £200m. The ships are Isle of Islay, Loch Indaal, Lochmor and Claymore.
The programme initially looked healthier. CMAL was highly satisfied with construction progress, and several shipbuilding milestones for the first two ferries came ahead of schedule. After the launch of the first two vessels, however, delays surfaced.
The original and revised timetable now reads:
- Isle of Islay: October 2024 original; January 2026 revised, 15 months late.
- Loch Indaal: February 2025 original; delivered 20 months late.
- Lochmor: June 2025 original; second quarter of 2027 revised.
- Claymore: October 2025 original; second quarter of 2027 revised.
The first vessel’s 15-month slip becomes 20 months on Loch Indaal, while Lochmor and Claymore move into the second quarter of 2027. This is no longer one late handover; it is a delivery sequence losing control after launch.
Why has the project slipped so far?
The delivery report cites “issues with the shipyard’s construction schedule” behind the delayed handover. Reports also link much of the programme’s slippage to Cemre Shipyard’s financial difficulties. CMAL had to put more money into the build before ownership changed hands.
CMAL had already made construction payments for all four vessels and covered an additional £20m in incremental shipbuilding costs. In June 2026, it took the extraordinary step of paying £23m to assume ownership of the three ferries Cemre was building for it; Loch Indaal had not yet been delivered at that point.
The arrangement protected shipbuilding costs already incurred and gave CMAL, as shipowner, the right to tow vessels under construction to other shipyards if Cemre went bankrupt. The ferries could then be completed, delivered and put into service. That is a costly contingency, not a clean transfer of risk.
The £23m payment buys CMAL an exit from a yard failure, but it does not restore the original schedule. One ship has now arrived; the other three still face moved construction and handover dates.
What remains in Cemre’s orderbook?
Glen Rosa, the second LNG dual-fuel ferry commissioned by CMAL, remains under construction at Cemre and is now eight years behind its original schedule. It sits outside the four diesel-electric ferries, but not outside the yard’s delivery risk.
Separately, CMAL placed an order earlier this year with CSSC Guangzhou Shipyard International (GSI) for two next-generation passenger/ro-ro (ro-pax) vessels. The ships will replace aging fleet vessels that have been in service for nearly three decades. The GSI order gives CMAL another yard for newbuild tonnage while the Cemre programme remains exposed.
The Loch Indaal handover is genuine, but it is not a clean bill of health for Cemre’s delivery record or CMAL’s timetable: one ship has escaped the yard; three sister ferries and Glen Rosa have not.
via Google News: Shipbuilding (Source)
More from Amara Osei
Show full bio
Senior reporter covering technology and product news in commercial shipping for industry professionals at Vessels.
160 articles
Linked entries
- CMAL takes delivery of Loch Indaal, 20 months late
- CMAL Takes Delivery of Delayed Islay Ferry MV Loch Indaal in Turkey
- CMAL warns direct ferry awards to Ferguson Marine are 'folly'
- Cmal warns direct ferry award to Ferguson Marine would be 'folly at worst'
- CMAL warns it would be 'folly' to give Ferguson Marine new ferry contracts