TCP commissioned a second 25 MVA transformer at Paranaguá on November 22, doubling substation capacity for R$7 million and clearing the path to 6,000 reefer plugs and 36 RTG conversions.

Second transformer doubles capacity at Paranaguá Container Terminal substation - DatamarNews
Exhibit · Second transformer doubles capacity at Paranaguá Container Terminal substation - DatamarNews — Roy Gwok / unsplash

Adjustments

  1. TCP commissioned a second transformer on November 22, doubling substation capacity from 25 to 50 MVA under a R$7 million investment.
  2. Reefer outlets will grow from 5,280 today to 5,500 by end-2026 and 6,000 by 2028.
  3. Converted RTG cranes cut emissions 97%, raised productivity 21% and cut maintenance costs up to 80%; 36 of 39 RTGs remain to be electrified.
  4. Two new ship-to-shore cranes are expected by 2028.
  5. TCP has held an I-REC renewable certificate for five consecutive years and was the first Brazilian terminal certified to ISO 50001.

A R$7 million investment has doubled the Paranaguá Container Terminal's substation capacity from 25 to 50 MVA, with the second transformer commissioned on Sunday, November 22 — without taking the substation offline.

The substation, which opened in 2023, was designed from the start for two 25 MVA units. TCP has now filled the second bay, and the extra power arrives with a queue of electric-hungry projects behind it.

What changes immediately?

Reefer plugs, for starters. The terminal counts 5,280 outlets today and plans to reach 5,500 by the end of 2026 and 6,000 by 2028. As reefer volumes climb, so does the load on the grid.

"As cargo volumes grow and we adopt new technologies, demand for electricity is likely to rise. Installing the second transformer immediately improves power quality and efficiency and prepares the terminal to expand its operations," said Kayo Zaiats, TCP's safety superintendent.

The capacity also feeds the fleet renewal plan:

  • Two new ship-to-shore cranes expected by 2028
  • Continued replacement of diesel equipment with electric models
  • Electrification of the remaining 36 rubber-tired gantry cranes in the yard

The RTG numbers doing the persuading

TCP runs 39 RTGs and has already converted three working the terminal's rail area. According to TCP, the converted units cut greenhouse gas emissions by 97% versus diesel, lifted productivity by 21% and trimmed maintenance costs by as much as 80%.

Those three cranes are, in effect, the business case for the other 36 — and for the substation that will power them.

"The results from the first RTGs reinforce the importance of extending electrification to other parts of the terminal. In addition to reducing our environmental impact, the technology improves productivity and reduces maintenance needs, showing that investments in sustainability can deliver significant gains in operating efficiency," Zaiats said.

The electrification push extends beyond the crane fleet. TCP has bought two electric buses, swapped the forklifts in its import warehouse for electric models, and is weighing purchases of electric terminal tractors and heavy-duty forklifts.

How do you install a transformer without stopping cargo?

Carefully, it turns out. The substation stayed in service throughout the installation and commissioning, with engineering teams sequencing the work to keep it safe. Some cargo operations ran during the works, sparing the terminal a full shutdown. With testing done and the unit's safety and performance verified, the substation now runs at its full planned 50 MVA.

The grid side of TCP's record is already established. The terminal has bought renewable electricity since 2021 and collected an international renewable energy certificate (I-REC) for the fifth consecutive year in 2026. TCP says it was also the first Brazilian port terminal certified to ISO 50001 for energy management.

Now it has the transformers to match the certificates.

via Google News: Ports & Terminals (Source)

Share this article:

More from Amara Osei

Amara Osei

Show full bio

Senior reporter covering technology and product news in commercial shipping for industry professionals at Vessels.

160 articles

Linked entries

  1. Rijeka picks Končar for 17.5 MW shore power at two terminals
  2. Engen-led consortium reaffirms R40bn Durban LNG terminal plan
  3. Durban Gateway races 20-day backlog with crane repairs and 70-unit fleet order
  4. Chennai woos Taiwanese carriers with $1.88bn terminal pitch
  5. 15+ Terminal Deals in Ten Months: Carriers Buy Their Way to Berths

▲ Previous article▼ Next article