Mozambique approves 18.6m t/y Rovuma LNG plan, up from 15.2m
Mozambique clears ExxonMobil's revised $26bn Rovuma LNG plan, lifting capacity to 18.6m t/y with 12 modular trains. FID and the EPC award still wait.

Adjustments
- Council of Ministers approved a revised plan raising Rovuma LNG capacity from 15.2m to 18.6m t/y
- INP says electric-driven modules cut emissions about 40% versus the 2019 plan; first production targeted 2031
- Government projects $121bn in state revenues over 25 years and 25% of output reserved domestically
- Saipem-led consortium (McDermott, Daewoo E&C, CPECC) got a letter of intent in August; EPC award awaits FID
Mozambique's Council of Ministers has approved a revised development plan for ExxonMobil's $26bn Rovuma LNG project, lifting proposed liquefaction capacity from 15.2m to 18.6m tonnes per year.
That is a 22% increase in nameplate capacity on a project that has spent years stuck between insurgency-driven delays and regulatory process. The approval clears another hurdle. It does not clear the big one: a final investment decision.
What does the revision actually change?
The amended plan, signed off by the Council of Ministers, keeps the basic architecture — offshore Area 4 gas in the Rovuma Basin piped to a proposed onshore LNG complex — but swaps in a different plant design.
The key numbers, per petroleum regulator Instituto Nacional de Petróleo (INP):
- Capacity: 18.6m tonnes per year of LNG, up from 15.2m t/y in the 2019 plan
- Configuration: 12 modular liquefaction units
- Power: electrically driven gas-processing modules, replacing the earlier mechanical setup
- Emissions: roughly 40% lower than the original 2019 plan
- Cost: INP says the revision cuts construction costs, without publishing a figure
- First production: still targeted for 2031
The claimed efficiency and cost gains deserve scrutiny. INP credits the electric drives for most of the emissions reduction, but the regulator has not published baseline numbers, and no independent estimate backs the 40% figure yet.
What's in it for Maputo?
The government's case rests on three numbers: $6bn, 25%, and $121bn.
Mozambique expects local companies to land approximately $6bn in supply and service contracts during the development. It has earmarked 25% of gas production for the domestic market. And it estimates the project could generate $121bn in state revenues over 25 years.
Take the $121bn with salt. That is a 25-year revenue projection built on production volumes, gas prices and fiscal terms that will all move before first cargo. Government forecasts for mega-projects tend to age badly; there's no published price deck behind this one.
Is the project actually moving?
The approval follows real progress on the contracting front. In August, a consortium led by Saipem — with McDermott, Daewoo Engineering & Construction, and China Petroleum Engineering & Construction Corporation — received an initial letter of intent for preliminary engineering and procurement work.
That is front-end money, not steel. The full engineering, procurement and construction award still hangs on a final investment decision, and ExxonMobil has not dated that decision.
So the scorecard reads: regulatory plan approved, capacity raised, contractors pre-positioned, domestic-supply quota set — but no FID, no EPC award, and first production still four years out at best. For a project first planned on 2019 assumptions, the 2031 target leaves little slack for further slippage.
The Council of Ministers' approval removes a paper obstacle. The commercial one — whether ExxonMobil and its Area 4 partners commit $26bn — remains, and nothing announced this week obliges them to.
via Splash 247 (Source)
More from James Calloway
Show full bio
Correspondent covering technology and product news in commercial shipping for industry professionals at Vessels.
44 articles
Linked entries
- Shell Warns IMO Delay on Green Fuel Rules Risks Stalling Bunker Investment
- EU ETS likely to survive any IMO zero-carbon deal, IBIA panel says
- Posorja terminal expands to 800m berth and 1.4m TEU capacity
- Clean Shipping Coalition Pushes for Net-Zero Framework Adoption at MEPC 85
- IMO Net-Zero Framework Stalls Again as US Blocks Carbon Penalties