MODEC joins Gato do Mato FPSO hull a month early, split across Japan and China

MODEC finished joining the Gato do Mato FPSO hull on November 26, 2026, almost a month early, pairing a Yokosuka-built bow with a Chinese stern for Shell's Orca project. First oil is expected in 2029.

How shipyards in Japan and China joined the hull of Shell’s Gato do Mato FPSO, which will operate in Brazil’s pre-salt f
Exhibit · How shipyards in Japan and China joined the hull of Shell’s Gato do Mato FPSO, which will operate in Brazil’s pre-salt f — MemoryCatcher / pixabay

Adjustments

  1. MODEC completed the Gato do Mato hull joining on November 26, 2026, nearly a month ahead of schedule
  2. The bow was built at Sumitomo Heavy Industries in Yokosuka and left Japan for China on July 2
  3. Afloat welding above the waterline achieved 99% acceptance in dimensional inspections and finished a week early
  4. The FPSO has a design capacity of 120,000 barrels per day and will work in about 2,000 meters of water at Orca
  5. Shell expects first oil at Orca in 2029

MODEC completed the hull joining of Shell's Gato do Mato FPSO (floating production, storage and offloading vessel) on November 26, 2026, nearly a month ahead of schedule, closing out a construction sequence that split the hull between a Japanese and a Chinese shipyard.

The forward section was built at Sumitomo Heavy Industries' yard in Yokosuka. On July 2, MODEC announced the bow section had left Japan for its partner shipyard in China, where the stern was under construction. MODEC's release at that stage showed only the forward part of the hull in transit.

Splitting the hull across two yards distributes workload and compresses the schedule, but it demands tight geometric discipline. For sections built in parallel to be joined later, both teams must work to the same design references. MODEC applied dimensional control — the verification that measurements and positions of the parts at the joint edges fall within the tolerances specified for assembly — as the binding discipline of the project.

How did the joining sequence run?

Welding of the two sections began in October with the hull afloat, an arrangement that avoids waiting for dock availability but leaves the underwater portions inaccessible. MODEC reported the work above the waterline was completed a week ahead of schedule, with 99% acceptance in dimensional inspections. The figure covers the measurement and alignment checks performed at that stage.

At the end of October, the vessel entered dry dock. With the bottom of the hull exposed, the team completed the welds that would sit below the waterline, installed the risers (the pipes connecting the subsea system to the platform) and carried out additional dimensional checks and tests to confirm the pipes were clear.

What comes next for the hull?

Hull joining completes the stage that assembled blocks manufactured in different countries. Integration and testing of onboard systems remain before the unit is ready for operation. The FPSO will be outfitted to produce, store and transfer oil.

The unit is destined for Shell's Orca project in the pre-salt region of the Santos Basin, roughly 200 km south of Rio de Janeiro in approximately 2,000 meters of water. MODEC lists a design capacity of 120,000 barrels of oil per day. Shell expects first oil in 2029.

A hull welded afloat, then finished in dock, on a schedule running ahead of plan — a modest template for how pre-salt tonnage is now being built.

via Google News: Shipbuilding (Source)

Share this article:

More from Rebecca Stone

Rebecca Stone

Show full bio

News editor covering people, launches and day-to-day practice in commercial shipping for industry professionals at Vessels.

174 articles

Linked entries

  1. HJ Shipbuilding to Build Offshore Wind Cluster on Idle Gunsan Land
  2. Boluda agrees Samskip deal, targeting 32-vessel short-sea network
  3. EDT Offshore orders methanol-ready subsea construction vessel from ZPMC
  4. KTU Shipyards starts steel cutting on ATB unit and two crane barges
  5. Hanwha Lands $269 Million Navy Deal for First Medium Landing Ship

▲ Previous article▼ Next article