Hanoi splits Cai Mep Ha port review between two agencies
Vietnam's construction ministry has split review of the VND 50,820bn Cai Mep Ha port between two agencies as the developer pushes to build five 24,000 TEU berths at once on 228 hectares.
Adjustments
- Cai Mep Ha port project totals VND 50,820 billion, with VND 7,623 billion investor equity from a Geleximco-ITC Corp-SCIC consortium.
- Developer proposes 5 main berths for ships up to 250,000 tons (~24,000 TEU) built simultaneously rather than in three phases.
- Phase 1 (2025-2030) targets first berth in Q4 2028 at ~2 million TEU/year; full build-out by 2050 reaches 10.8 million TEU/year.
- Company requests allocation or lease of ~228 hectares under HCMC Decision No. 703/QD-UBND of January 30, 2026.
- Ministry of Construction assigned the Maritime and Inland Waterways Administration and the science/technology department as focal points on 2021-2030 port plan revision.
Vietnam's Ministry of Construction has split the review of the VND 50,820 billion Cai Mep Ha port project between two of its own agencies, moving the "mega" terminal plan one bureaucratic step forward without approving anything. The Vietnam Maritime and Inland Waterways Administration will handle port planning questions; the Department of Science, Technology, Environment and Construction Materials takes land and sea-area issues.
That's the whole development. No decision, no timeline, no budget change.
What did the ministry actually order?
The Maritime and Inland Waterways Administration will work with the Ho Chi Minh City People's Committee to study solutions while HCMC revises its detailed maritime and port infrastructure plan for 2021-2030, with a vision to 2050. The developer's requests sit inside that revision, so the answer depends on a planning document still being rewritten.
The environment and materials department leads advice on the land and sea-area questions, in line with the law. The ministry also told Cai Mep Ha International Port JSC to submit complete records and to explain and cooperate with the reviewing agencies. A caveat the source doesn't spell out: "cooperate fully" usually means the file was incomplete.
What does the company want?
The developer asked to build five main berths at once, each capable of taking container ships up to 250,000 tons — roughly 24,000 TEU. Two auxiliary berths would serve vessels of 70,000-150,000 tons.
The rationale is fleet-driven. Carriers are fielding ships of 18,000-24,000 TEU on Asia-Europe and Asia-America strings, which demand longer berths, deeper drafts and higher handling capacity than Vietnam currently offers for transshipment. The investor says shipping lines want the terminal built synchronously rather than in the approved three phases, because an 8-10 year phased rollout gives them no basis for network planning or long-term route commitments.
The company also wants allocation or lease of the project's entire remaining land and sea area — approximately 228 hectares — inside boundaries set by HCMC People's Committee Decision No. 703/QD-UBND dated January 30, 2026. Securing that tenure, the developer argues, creates the legal basis to build everything at once and to reuse dredged material on site, cutting capital cost. The savings figure is not quantified in the document.
There is a capacity gap driving the urgency. Phase one capacity of roughly 2 million TEU per year, about 6-8 voyages a week, reportedly falls short of what some carriers want before committing transshipment volumes to Vietnam.
Who is building it, and on what schedule?
The project sits in Tan Phuuc ward, Ho Chi Minh City. Total investment is VND 50,820 billion, with the investor consortium contributing about VND 7,623 billion — roughly 15 percent equity — and the rest mobilised capital.
On January 30, 2026, the HCMC People's Committee issued Decision No. 703/QD-UBND approving the investment policy and the consortium itself: Geleximco Group Joint Stock Company, International Transport and Trade Joint Stock Company (ITC Corp), and the State Capital Investment and Business Corporation (SCIC).
The approved schedule still reads:
- Phase 1: 2025-2030, first berth operational in Q4 2028, capacity about 2 million TEU/year
- Phase 2: 2031-2040
- Phase 3: 2041-2050, full build-out reaching approximately 10.8 million TEU/year
What does this change for carriers?
Right now, nothing. The company's synchronous-build proposal, the 228-hectare land request and the five-berth configuration all remain requests under review. The phased plan and the 10.8 million TEU end-state stay on paper as the only approved baseline.
The one hard consequence: any carrier planning transshipment through Cai Mep Ha before 2031 is now waiting on two ministries, a city planning revision and a land handover — not on berth availability, which the phased schedule already pushes to late 2028 at the earliest.