Ghana has instructed customs and terminal operators to separate shipping-line releases from clearance, easing a process that has left some Tema importers waiting four to five days.

Adjustments
- Nov. 20, 2026: Ghana disclosed the directive at a GIFF meeting in Tema.
- Implementation covers GRA’s Customs Division and terminal operators.
- Cleared importers can collect goods without separate shipping-line approval.
- Some importers still wait four to five days for release documentation.
- A growing number of empty containers awaiting carrier return are adding storage pressure.
By Tom Whitfield
Ghana has told customs and terminal operators to let cleared cargo leave without separate shipping-line approval, targeting release waits that have reached four to five days at Tema Port. The change aims to ease congestion and speed cargo evacuation.
Victor Kofi Baidoo, head of the Revenue Assurance Department at the Ministry of Finance, disclosed the directive at a Friday, November 20, 2026 meeting with members of the Ghana Institute of Freight Forwarders (GIFF) in Tema. The meeting formed part of the Ministry’s engagements with freight forwarding stakeholders on port bottlenecks and trade facilitation.
The instruction covers the Customs Division of the Ghana Revenue Authority (GRA) and terminal operators. It divides the customs process from the carrier’s release procedure, removing the previous requirement to complete both before taking delivery.
Under the old sequence, an importer could finish customs work and still wait inside the terminal for the carrier’s documents. The directive leaves outstanding carrier transactions to be handled separately. It changes the gate for physical cargo pickup rather than cancelling commercial obligations.
What changes for importers?
Importers that have paid their duties and completed customs clearance can collect their goods without waiting for separate approval from a shipping line (ocean carrier). Baidoo said the new process would allow “cargo evacuation to proceed once customs requirements have been met,” while outstanding carrier transactions remain separate.
Customs and terminal operators have received the directive for implementation. It should shorten the time cleared containers occupy terminal space, improve container turnaround (how quickly a box moves from discharge to onward availability) and make room for more incoming consignments.
For terminal operators, the gain comes from releasing boxes that already meet customs requirements. The directive routes outstanding carrier transactions through a separate process, rather than holding compliant cargo at the terminal.
The government expects the measure to speed cargo evacuation, free up storage space and reduce avoidable costs for importers. It could also reduce demurrage (charges for containers held beyond the permitted period) and other avoidable charges caused by delayed collection.
How long can release delays still take?
Johnny Mantey, a freight forwarder and leading GIFF member, welcomed the change as “a significant step towards addressing congestion at the Tema Port.” Freight forwarders had long argued for the separation, according to Mantey.
The remaining problem is the release practice of some shipping lines. Importers can still wait four to five days for the necessary documentation, even after they have paid duties and secured customs clearance. Mantey described those delays as a major challenge for freight forwarders.
Empty containers add to the strain. A growing number are awaiting return to shipping lines, and Mantey said they are putting pressure on available storage at the port.
Mantey urged shipping lines to cooperate on timely cargo evacuation and the return of equipment. He warned that continued delays could make congestion worse. Further engagements with the carriers are planned to address the outstanding release, storage and return problems.
The measure does not erase the need to settle transactions with shipping lines. It changes their sequence: customs clearance now opens the route to cargo pickup, while the commercial and documentary work with the carrier proceeds on a separate track.
That is the practical test at Tema. The government has removed a duplicate gate, but four-to-five-day waits and rising empty-container stock will determine whether the change improves yard capacity and container turnaround.
via Google News: Container Shipping (Source)
More from Tom Whitfield
Show full bio
Staff writer covering companies, deals and strategy in commercial shipping for industry professionals at Vessels.
93 articles
Linked entries
- Ghana separates shipping-line releases from customs at Tema Port
- Duty-paid cargo to leave Tema without shipping-line approval
- CENTCOM Warning: STS Transfers of Iranian Cargo Now Risk Seizure
- Togo to Upgrade 40 km Lomé Port–Adétikopé Rail Line in 2027
- CENTCOM Widens Iran Blockade to Ship-to-Ship Cargo Receivers