Ghana separates shipping-line releases from customs at Tema Port
Ghana’s GRA and terminal operators will separate shipping-line cargo release from customs clearance, targeting four-to-five-day waits and storage pressure, with lower demurrage expected at Tema Port.

Adjustments
- On November 20, 2026, Ghana directed the GRA’s Customs Division and terminal operators to separate shipping-line release from customs clearance.
- Some importers wait four to five days for shipping-line release documents after completing customs procedures.
- The new process allows delivery once customs requirements are met; outstanding shipping-line transactions remain separate.
- Expected gains include shorter terminal stays, faster container turnaround, more storage capacity and lower demurrage.
- Further meetings with shipping lines are planned to address release and container-return delays.
By Tom Whitfield
Some importers at Tema Port have waited four to five days for shipping-line release documents after paying duties and completing customs clearance, the bottleneck Ghana now targets.
The government has directed the Customs Division of the Ghana Revenue Authority (GRA) and terminal operators to decouple shipping-line release procedures from customs clearance. Importers meeting the customs requirements can take delivery without waiting for a separate release approval from their shipping line.
Victor Kofi Baidoo, head of the Revenue Assurance Department at the Ministry of Finance, announced the directive on Friday, November 20, 2026. He addressed members of the Ghana Institute of Freight Forwarders (GIFF) in Tema during consultations on port congestion and trade facilitation.
What changes for importers?
The former process required importers to secure shipping-line release approvals even after completing customs procedures and settling all applicable duties. The new arrangement allows cargo to leave once customs requirements have been fulfilled.
The change addresses two release steps that previously ran in sequence. Importers completed customs procedures and paid the applicable duties; the shipping line then controlled a separate approval for collection. The directive removes the second gate from the delivery sequence once customs has cleared the cargo.
Baidoo said: “Any outstanding transactions between importers and shipping lines would then be dealt with independently.” The government has communicated the directive to Customs and terminal operators for implementation.
That separation matters because a cleared container can still occupy scarce terminal space while awaiting a carrier document. Importers do not have to resolve every shipping-line transaction before taking delivery. Those transactions proceed independently of the customs release.
What should improve at the terminal?
The government expects the separation to reduce the time cleared containers remain at terminals and improve container turnaround times. The policy could also free storage capacity for incoming cargo and reduce delay-related costs for importers.
Key expected effects include:
- A shorter stay for containers that have cleared customs.
- Faster container turnaround and steadier access to terminal space.
- Lower demurrage (charges for holding containers beyond the agreed free period) and other costs caused by delayed delivery.
The directive leaves customs requirements unchanged. Importers must complete clearance and settle applicable duties before collection. It does not cancel outstanding shipping-line transactions, which Baidoo said would be handled independently after customs clearance.
Why does release still matter?
Johnny Mantey, a leading GIFF member, welcomed the directive and called it “an important intervention in efforts to address congestion at the Tema Port.” He said freight forwarders had repeatedly sought the separation because the previous arrangement contributed to cargo evacuation delays.
Mantey identified persistent document delays from some shipping lines. Importers sometimes spend between four and five days obtaining the necessary approvals, even though they have completed customs procedures and paid the required duties.
He also highlighted the growing stock of containers awaiting return to shipping lines, particularly empty units. Their accumulation adds pressure to Tema Port’s limited storage capacity and leaves less room for incoming cargo.
What must shipping lines do?
Mantey called on shipping lines to cooperate with the new arrangement. He asked them to evacuate and return containers promptly, preventing further congestion. The government will also hold additional engagements with shipping lines to resolve the remaining release and return challenges.
For terminals, faster evacuation should free storage and reduce demurrage exposure. For importers, it offers a shorter path from cleared cargo to collection. The policy’s congestion benefit now depends on operational compliance at Tema Port.
via Google News: Container Shipping (Source)
More from Tom Whitfield
Show full bio
Staff writer covering companies, deals and strategy in commercial shipping for industry professionals at Vessels.
93 articles
Linked entries
- Ghana separates carrier releases from customs clearance at Tema Port
- Duty-paid cargo to leave Tema without shipping-line approval