First Boxship Unloads at Thilafushi as Malé Port Relocation Begins

MSS Galina discharged 490 of its 524 boxes at Thilafushi, a first for the Maldives. MPL targets full Malé port relocation by November 2026 with 390,000 TEU capacity.

Cargo unloading from container vessels begins at Thilafushi - Edition.mv
Exhibit · Cargo unloading from container vessels begins at Thilafushi - Edition.mv — Artan / unsplash

Adjustments

  1. MSS Galina brought 524 containers, with 490 TEU scheduled for discharge at Thilafushi.
  2. China Harbour Engineering Company's 375-meter quay wall is due for completion by end of July 2026.
  3. The 60-hectare Thilafushi port will add 390,000 TEU annual capacity, lifting national capacity to 1.8 million TEU.
  4. All Malé commercial port operations are slated to relocate in November 2026.
  5. Two ship-to-shore cranes and one mobile harbor crane will be installed at opening.

Container unloading has officially begun at Thilafushi Cargo Terminal, with the 524-box vessel MSS Galina discharging 490 TEUs directly at the Maldives' newest facility. Maldives Ports Limited (MPL) confirmed the call marks the first time a large container-carrying vessel has docked and worked cargo at Thilafushi, where the operations of Malé Commercial Harbour are being fully relocated.

MSS Galina arrived in the Maldives with 524 containers of cargo, of which 490 TEU are scheduled for discharge at Thilafushi, according to MPL. The company called the operation a very strong and successful foundation for the wider relocation project.

Why now?

MPL began planning and preparation work for the move in May this year. The timing wasn't accidental. Around the New Year and for up to one month after Ramadan ends, the volume of goods imported into the Maldives rises significantly, MPL said. The expansion of the tourism sector, growing bed capacity and the opening of new resorts compound that import surge.

The driver is capacity. MPL says one of the biggest purposes of expanding Thilafushi operations is to relieve the space constraints choking the Malé commercial port, and to let businesses clear goods as quickly as possible without difficulties.

What does the full relocation look like?

Practical work on moving Malé's commercial port entirely to Thilafushi is progressing rapidly. China Harbour Engineering Company is building the initial 375-meter quay wall, with completion projected by the end of July next year. MPL aims to relocate all Malé commercial port operations to Thilafushi in November next year and begin services at a modern standard.

The project's headline numbers:

  • The 60-hectare Thilafushi port will handle containers at a capacity of 390,000 TEUs per year, raising national container capacity to 1.8 million TEUs per year.
  • It opens with a 375-meter international container quay wall at 14.6 meters depth, extendable to 1.4 kilometers.
  • A domestic-vessel quay wall of roughly more than two kilometers will be built.
  • The international quay wall should cut vessel loading and unloading to a turnaround time of approximately two days.
  • Two ship-to-shore quay cranes and one mobile harbor crane will be installed when the port opens.

How far along is construction?

Work on the first 100 meters of the quay wall dedicated to domestic vessels is complete, and roughly 40 percent of backfilling on the reclaimed area behind that domestic wall is done. Precast concrete blocks for the quay wall are being produced on-site, machinery and equipment are being procured, and a contractor for the terminal buildings is being selected.

President Dr. Mohamed Muizzu has said Thilafushi Port will be four times the size of the Malé commercial port and that it is the largest economic project currently underway in the Maldives.

For operators calling the Indian Ocean archipelago, the sequencing matters. Discharge at Thilafushi is live now, the 375-meter international berth follows in July 2026, and full port operations with the crane infrastructure move in November 2026. That two-day turnaround target, if met, will reshape scheduling assumptions for services currently working the congested Malé harbour.

via Google News: Ports & Terminals (Source)

Share this article:

More from Tom Whitfield

Tom Whitfield

Show full bio

Staff writer covering companies, deals and strategy in commercial shipping for industry professionals at Vessels.

163 articles

Linked entries

  1. Vizhinjam links 1,500-tonne MRF rubber cargo to Kottayam ICD
  2. 1,500 Tonnes of African Rubber Headed from Vizhinjam to Kottayam ICD for MRF
  3. Durban Gateway races 20-day backlog with crane repairs and 70-unit fleet order
  4. OMSB targets 2027 start for Pilbara coastal container service
  5. Caerus Shipping launches Arab Sea Express linking Sohar and India

▲ Previous article▼ Next article