Cook Strait ferries take shape as port costs triple to $1.9b
Two rail-enabled hybrid ferries from Guangzhou Shipyard are locked at $596m fixed-price for 2029 delivery, but port works have tripled, pushing the Cook Strait programme to $1.9b.

Adjustments
- Two rail-enabled hybrid ferries cost $596m fixed-price from Guangzhou Shipyard International, due 2029
- Total programme cost is $1.9b; port works at Wellington and Picton rose to $409m and $493m from $167m and $110m
- Each vessel: ~200m, 1,500 passengers, 2.4km of vehicle lanes, 40 rail wagons, 30-year life
- Gateway review names inter-party relationship management as the biggest single risk
- Transporting New Zealand estimates $30b of freight crosses Cook Strait annually
New Zealand's Cook Strait ferry replacement programme now has a fixed-price number attached to its ships: $596m for two hybrid, rail-enabled vessels from Guangzhou Shipyard International, due in 2029. The land side is the problem. Total programme cost sits at $1.9 billion after port works roughly tripled, and the government is already drafting a fallback plan.
Ferry Holdings' updated Statement of Intent, unveiled this week, finally gives freight operators something to plan around after years of cancellations, reviews and ministerial point-scoring.
What do the ships actually deliver?
Each vessel runs about 200 metres long, carries around 1,500 passengers, offers 2.4km of vehicle lanes and takes up to 40 rail wagons. Rail freight loads straight on, cutting out handling steps that add cost and time on every crossing. Design life is 30 years.
The specification leans green and resilient:
- Solar panels and a battery storage system, with a methanol option later
- 30 percent lower carbon per passenger and unit of cargo
- LIDAR bridge technology
- Redundant propulsion, steering and power, sized for the tight waters of the Marlborough Sounds and Wellington Harbour
Ferry Holdings chair Chris Mackenzie points to the redundancy package as the safety core of the design. Interislander's operations chief Taru Sawhney says staff are "in full planning mode" for the transition.
The shipbuilding contracts, signed in November 2025, are fixed-price. That matters. It removes the shipyard blowout risk that helped sink iReX, the previous scheme whose costs ran toward $4 billion before cancellation.
Where did the money go?
Here the story turns. Treasury reviews in May 2026 put the Wellington works at $167m and Picton at $110m. By July, BusinessDesk reported those figures had risen to $409m and $493m respectively, alongside $426m in programme management and contingency.
The programme hit the government's $1.7b ceiling in June, forcing out some value-for-money, sustainability and safety enhancements. Port of Marlborough ($110m) and CentrePort ($100m) chipped in to keep the taxpayer share under the cap. Minister Winston Peters said the government had "only added cost where the taxpayer and ratepayer was not paying, where it added commercial value." Those port contributions will be recovered through port charges on KiwiRail — which ultimately means freight customers pay them back.
Critics saw this coming. In 2025, BusinessDesk's Pattrick Smellie called it the back-to-front ferry deal: ships ordered from China before port designs and costings existed, with Tasmania's stranded new ferries as the obvious warning. In May 2026, The Post reported a Treasury-led review found the land-side works carried "unacceptable levels of risk," after the plan to reuse existing CentrePort assets collapsed when several proved too degraded to salvage.
Mackenzie is openly preparing for slippage. "We will start alternative operational contingency planning with KiwiRail in 2027, to be activated should risks increase and erode available time contingency," he said.
Is it on schedule?
For now, yes. October's Gate 3 Gateway review found the programme "progressing well" and within its funding envelope. Port works remain on schedule for 2029, with Wellington deconstruction finishing in March 2027 and Picton's new wharf construction starting in February 2027. CentrePort's 2026 annual report describes a staging wharf on Southern Road and new piling already under way. Treasury's proactive release shows near-monthly oversight through 2026.
But the same Gateway review flags incomplete final designs and unresolved contracts for major works. It names relationship management between delivery parties as the single biggest risk, ahead of marine conditions. That is a governance problem, not an engineering one, and it is exactly where political churn does the most damage.
What should freight businesses plan for?
The stakes are large. In 2025, Transporting New Zealand estimated about $30 billion of freight crosses Cook Strait each year. Its Billy Clemens warned then that with only four ferries operating, operators would have to manage capacity carefully "or we will see price hikes and costly delivery delays for businesses and consumers." He also wanted the party politics parked in favour of delivery.
That remains the right ask. Treat 2029 as a credible upgrade date. Budget for tight capacity until then, and for a possible delay if the wharves slip. The ships are bought and paid for. Over the next two years, the test is whether Ferry Holdings, KiwiRail and two port companies can pour concrete as reliably as a Chinese shipyard welds steel — and whether whoever governs after 2026 leaves them alone while they do it.
via Google News: Shipbuilding (Source)
More from Tom Whitfield
Show full bio
Staff writer covering companies, deals and strategy in commercial shipping for industry professionals at Vessels.
165 articles
Linked entries
- Boluda agrees Samskip deal, targeting 32-vessel short-sea network
- US towboat fleet expansion accelerates on stronger cargo demand
- ABB wins order to power third WSF hybrid-electric ferry newbuild
- Japan’s proposal could dilute IMO’s $15bn Net-Zero Framework
- OMSB targets 2027 start for Pilbara coastal container service