Cádiz completes 870m tunnel link for new container terminal
Cádiz has linked the full 870m tunnel for its new container terminal access road. Civil works target summer 2027, with tunnel installations due in the fourth quarter.

Adjustments
- The 1.2 km access road includes an 870m tunnel, largely beneath land used by Navantia.
- Contractors excavated the remaining 150m over 2.5 months and removed about 10,000 cu m.
- Civil works are due by summer 2027, with tunnel installations scheduled for Q4 2027.
- Construction began in November 2014; the original contract ended in June 2017 after technical problems flooded the partly built tunnel.
- A freight railway platform under development above the tunnel will strengthen the terminal’s intermodal links.
Cádiz’s 1.2 km access road for its new container terminal now has a continuous tunnel connection, the Port Authority of the Bay of Cádiz (APBC) confirmed. Contractors excavated the remaining 150 metres over 2.5 months. They removed approximately 10,000 cu m (cubic metres) of material.
The breakthrough closed the gap between two previously separated tunnel sections. APBC said construction can now enter its final phase.
What does the tunnel breakthrough change?
The connection completes the full 870-metre tunnel along the planned access road. Most of the tunnel runs beneath land used by shiprepair company Navantia. The route now has structural continuity along its entire length. APBC’s remaining package spans paving, tunnel equipment, surface road connections and modifications to surrounding infrastructure, keeping unfinished road works distinct from the completed structural link.
Civil works are expected to finish by summer 2027. Tunnel installations are scheduled for the fourth quarter of that year. The milestone removes the structural break in the route. It does not complete the wider access scheme.
What caused the long construction history?
Construction began in November 2014. The original contract was terminated in June 2017. Technical problems had left the partially completed tunnel flooded. The chronology links the 2017 contract termination and subsequent flooding to an extensive rehabilitation programme that APBC has carried out since 2019 at the port.
Its scope included drainage, structural reinforcement and ground stabilisation. The breakthrough follows that rehabilitation work. The 2027 target separates civil construction from equipment installation.
How is the access road arranged?
The new road will measure 1.2 km. It includes 870 metres of tunnel. By placing most of the 870-metre tunnel beneath land used by Navantia, the project connects terminal access while separating heavy container movements from adjacent shipyard operations.
That separation should improve road access to the new container terminal. APBC describes the tunnel as the means to separate those traffic streams. The tunnel’s transport function is broader than completing an excavation. The design keeps heavy container traffic out of the Cádiz shipyard operating environment.
What will sit above the tunnel?
A freight railway platform is being developed above the tunnel. It will strengthen the new terminal’s intermodal (road-and-rail freight) connections. The combination of a road tunnel below and a freight railway platform above gives the terminal two freight access modes within the same landside works.
APBC says the milestone brings Cádiz closer to completing the infrastructure needed for expanded container operations. The rail work remains under development. The platform sits directly above the road connection. That pairing brings road and rail freight into the same terminal access project.
Which works remain before completion?
APBC expects civil works to finish by summer 2027. Tunnel installations are scheduled for the final quarter of 2027. The remaining scope covers four items:
- Paving.
- Tunnel equipment installation.
- Surface road connections.
- Modifications to surrounding infrastructure.
The 2027 programme therefore has two distinct deadlines: completion of civil works by summer and installation work during the fourth quarter, with several access-road elements still outstanding.
The milestone clears the tunnel connection, but not the wider access-road completion. APBC frames the breakthrough as entry into the project’s final phase. Together, those works are meant to deliver the terminal’s intended road connection and stronger rail connection. The schedule now offers separate targets for physical works and equipment installation.
via Google News: Ports & Terminals (Source)
More from Tom Whitfield
Show full bio
Staff writer covering companies, deals and strategy in commercial shipping for industry professionals at Vessels.
193 articles
Linked entries
- Port La Nouvelle expansion enters final stage as basin depth nearly doubles
- Lomé Container Terminal Wraps CFAF 13 Billion Quay Upgrade
- Suez regains 60% of Asia-Europe capacity amid Bab al-Mandab risk
- NextGeo Wins $12.7M Survey Contract for Spain-France Hydrogen Link
- Mexico City green-lights first phase of $6.26bn Manzanillo build-out