Port La Nouvelle expansion enters final stage as basin depth nearly doubles

DEME's Q3 update confirms Port La Nouvelle's expansion has entered its final stage, with basins deepened from 8.6m to about 16m and all three new terminals commissioned as partner search runs to 2027.

France's Port La Nouvelle expansion enters final stage as operations ramp up - Baird Maritime
Exhibit · France's Port La Nouvelle expansion enters final stage as operations ramp up - Baird Maritime — dendoktoor / pixabay

Adjustments

  1. Port La Nouvelle expands from 60 to 210 hectares; basins deepen from 8.6m to about 16m.
  2. Dredged depth is 15.9m below chart datum at the P10–P11 project cargo and P13–P14 Ro-Ro quays; Euroports lists 14.5m max draught at end-2026.
  3. Neptune Lines' Lake Taupo made the first Ro-Ro call in December 2025, discharging 1,500 vehicles.
  4. Euroports seeks terminal partners, with expressions of interest due by January 31, 2027.
  5. SEMOP Port La Nouvelle has operated the port since May 2021 under a 40-year concession prioritising offshore wind and green hydrogen.

Port La Nouvelle's expansion on France's Mediterranean coast has entered its final stage, DEME Group confirmed in its third-quarter trading update on Tuesday, November 17. Operations are ramping up across the enlarged facility, though "final stage" is doing some heavy lifting — several commissioning milestones remain open into 2026 and beyond.

The project expands the commercial port from 60 to 210 hectares and deepens its basins from 8.6 metres to roughly 16 metres. Terminal operator Euroports lists a maximum vessel draught of 14.5 metres at the end of 2026. That's the operative number for charterers; the dredged figure of 15.9 metres below chart datum applies at the P10–P11 project cargo quay and the P13–P14 Ro-Ro quay.

What's already working?

All three new terminals — project cargo, Ro-Ro and liquid bulk — were commissioned, Euroports announced in July. The traffic history so far is thin but real:

  • First Ro-Ro call: December 2025, when Neptune Lines' Lake Taupo discharged 1,500 vehicles.
  • First liquid bulk vessel: the P1 berth received it on June 25.
  • Project cargo terminal: two heavy-duty quays, the 250-metre P12 and the 300-metre P10–P11, with 11.5 metres depth at the foot of P12.

The project cargo terminal has already supported assembly work for the Eolmed and Éoliennes Flottantes du Golfe du Lion (EFGL) floating wind pilots. So the offshore wind pipeline isn't hypothetical — it's on the quayside.

Who gets the terminal capacity?

Euroports is now shopping for industrial, logistics and maritime partners for the terminal, with expressions of interest due by January 31, 2027. The call excludes floating wind activities in France, including those tied to the AO6 and AO10 tenders, which are handled separately. Read the exclusion twice: the port's flagship sector sits outside this particular tender, and nobody at DEME or Euroports has said publicly what the AO6/AO10 allocation process will deliver or when.

Who runs the port, and why wind and hydrogen?

SEMOP Port La Nouvelle has operated the facility since May 2021 under a 40-year concession that prioritises offshore wind and green hydrogen. In August, the port was among five French ports selected for offshore wind infrastructure funding — a state signal, though the sums and disbursement timetable were not disclosed in the material at hand.

The hydrogen angle has one named partner. The port has explored a floating hydrogen import terminal with Höegh Evi. That's "explored", not committed — no FID, no berth assignment, no date.

What changes for operators?

For shipowners and charterers, the story is draught and berth length. A 14.5-metre draught limit and 300 metres of heavy-duty quay put Port La Nouvelle in range of mid-size project cargo tonnage and Ro-Ro strings that previously had no Aude-coast option. The liquid bulk berth adds a third cargo stream.

The caveat is volume. One 1,500-vehicle Ro-Ro discharge and one liquid bulk call don't make a trade lane. The partner search running to January 2027 tells you Euroports itself doesn't yet know who will fill the 210 hectares. The dredging is done on paper; the orderbook for calls is not.

via Google News: Ports & Terminals (Source)

Share this article:

More from James Calloway

James Calloway

Show full bio

Correspondent covering technology and product news in commercial shipping for industry professionals at Vessels.

109 articles

Linked entries

  1. Nova Marine buys 25% of Terminal Nord in Ravenna
  2. Long Beach clears 937,000 TEUs in October, up 5% on record pace
  3. Three bidders vie for Rs 117.33bn VOC marine package
  4. SeaRoad finally takes delivery of EUR 100m RoRo SEAROAD I
  5. Port of Blyth unveils 3-hectare plan and 1m channel deepening

▲ Previous article