SeaRoad finally takes delivery of EUR 100m RoRo SEAROAD I

Flensburger delivers the EUR 100m, 3,790-lane-metre LNG dual-fuel SEAROAD I nearly three years late after insolvency; SeaRoad sails her to Melbourne–Devonport in January.

SEAROAD I finally delivered from Flensburger Shipyard - Shippax
Exhibit · SEAROAD I finally delivered from Flensburger Shipyard - Shippax — analogicus / pixabay

Adjustments

  1. SEAROAD I delivered by Flensburger Shipyard nearly three years behind the Q4 2023 contractual date
  2. Contract signed September 2021, worth EUR 100 million
  3. 41,996 GT, 12,539 dwt, 3,790 lane metres plus 101 cars
  4. Two Wärtsilä 9L46DF engines, 20,600 kW combined, LNG Type C tank
  5. Joins Melbourne–Devonport service in January under Australian flag

Flensburger Shipyard has delivered the EUR 100 million RoRo SEAROAD I to SeaRoad Shipping — nearly three years behind the contractual date, after the German yard went through insolvency and a takeover by the Heinrich Rönner Group.

SeaRoad signed the newbuilding contract in September 2021, with delivery originally due in the fourth quarter of 2023. The 41,996 GT vessel emerged as the last RoRo ship built in Northern Europe, and the Australian owner will sail her from Flensburg to join the Melbourne–Devonport, Tasmania service in January under the Australian flag.

What does the ship carry?

The 210m vessel, with a 29.3m beam, 6.35m draught and 12,539 dwt, carries four RoRo decks configured for mixed cargo:

  • Double-stacked cassettes weighing up to 100t each
  • Road trailers
  • New vehicles

Total capacity comes to 3,790 lane metres plus 101 cars. Cargo handling runs through a wide stern ramp/door, with fixed internal ramps connecting the decks. No lifts, no gimcracks — a workhorse layout for a Bass Strait crossing.

What drives her?

Wärtsilä supplies the propulsion package: two 9L46DF dual-fuel main engines delivering a combined 20,600 kW, driving twin controllable-pitch propellers. The Type C LNG tank comes from Wärtsilä as well, so the gas chain is a single-vendor affair.

Not SeaRoad's first dance with FSG

SeaRoad knows the Flensburg delivery slip firsthand. Its previous LNG dual-fuel newbuilding, the 25,409 GT SEAROAD MERSEY II, came out of the same yard in November 2016 — on a rather more conventional timetable.

The yard's insolvency and rescue by the Rönner Group turned the SEAROAD I order into a waiting game. The ship is finally afloat, built, and paid for; whether the last-RoRo-in-Northern-Europe tag becomes a milestone or an epitaph for regional RoRo construction is a question for the orderbook, not the delivery speech.

January will tell the operational story, when SEAROAD I berths at Devonport.

via Google News: Shipbuilding (Source)

Share this article:

More from Amara Osei

Amara Osei

Show full bio

Senior reporter covering technology and product news in commercial shipping for industry professionals at Vessels.

88 articles

Linked entries

  1. Europe's first modular warship prototype launches in Estonia
  2. Boluda agrees Samskip deal, targeting 32-vessel short-sea network
  3. Saronic signs $100m+ Syncrolift shiplift deal for Port Alpha yard
  4. Estonia launches 45-metre Euroguard warship in €95m consortium build
  5. Cool Carriers adds world's first gate-rudder reefer, Snow Land

▲ Previous article▼ Next article