VOC Port opens 442.5m Berth No. 10 with first Duqm call
VOC Port opened Berth No. 10 in Thoothukudi, with a 442.5m quay and 10.22m-tonne annual capacity. The 19 November 2026 trial served Duqm, not a throughput forecast.
Adjustments
- 10.22 million tonnes: stated annual cargo-handling capacity of Multi-Cargo Berth No. 10
- 442.5 metres: completed quay length, against an approximately 440-metre December 2024 outline
- 19 November 2026: SCL Mercury completed the trial berthing with project cargo bound for Duqm
- ₹80 crore: estimated cost of the December 2024 EPC plan
- 600,000 TEU: annual capacity of JM Baxi-operated Tuticorin International Container Terminal
By James Calloway
VOC Port lists 10.22 million tonnes of annual handling capacity for its new Multi-Cargo Berth No. 10, but SCL Mercury’s trial berthing does not establish throughput at that level.
What did the first call prove?
VOC Port commenced operations at the berth in Thoothukudi, Tamil Nadu, with the SCL Mercury’s successful trial berthing on 19 November 2026. The vessel’s project cargo shipment was bound for the Port of Duqm in Oman. That move marked the facility’s first operational milestone.
The completed quay measures 442.5 metres. VOC Port designed the berth for project cargo, machinery and general cargo. It adds waterfront capacity alongside the port’s container and bulk-cargo facilities while presenting another berthing option at southern Tamil Nadu’s gateway. The Duqm shipment demonstrates the intended overseas industrial-cargo role. It does not establish a regular cargo stream.
- Annual cargo-handling capacity: 10.22 million tonnes
- Cargo types: project cargo, machinery and general cargo
- Inaugural destination: Port of Duqm, Oman
- Trial vessel: SCL Mercury, 19 November 2026
The 10.22 million tonnes is stated handling capability, not a forecast of immediate throughput. The announcement provides no cargo volume for the trial call, no vessel schedule and no ramp-up target. VOC Port frames the addition as support for industrial shipments and export-import trade. Those claims now await operating evidence.
What did the December 2024 plan promise?
VOC Port outlined Berth No. 10 in December 2024 as part of a broader programme to accommodate additional bulk and breakbulk vessels. The proposal called for a berth of about 440 metres under the engineering, procurement and construction model, with an estimated cost of ₹80 crore. The completed quay measures 442.5 metres. It is 2.5 metres longer than the outline’s nominal 440 metres, though that original figure was approximate.
The December plan recorded an existing draught of 10.70 metres and proposed subsequent dredging to 14.50 metres. Those figures describe the earlier proposal. They do not confirm Berth No. 10’s current permissible operating draught.
How did reclamation support the facility?
In May 2025, VOC Port identified an 8.6-hectare area associated with the proposed berth and its storage yard. The same update said successive capital-dredging programmes had reclaimed about 146 hectares.
VOC Port said those areas supported “container terminal backup facilities, coal storage, windmill blade storage and other planned industrial uses.” Dredging completed in May 2025 used approximately 800,000 cubic metres of material to create 11.5 hectares of additional land for cargo storage.
The port said this approach “allowed material removed from navigational areas to support the development of shore-side infrastructure.” That links dredging to usable land. It does not show how much reclaimed material serves Berth No. 10 directly.
What wider harbour works sit behind the first call?
In May 2025, VOC Port completed two access works:
- Dredging in front of North Cargo Berth III to a draught of 14.20 metres
- An inner-harbour turning-circle expansion from 488 metres to 550 metres
The port said these works facilitate larger bulk carriers and container vessels. Together, they form part of wider harbour improvements addressing marine access and cargo handling.
Container capacity expanded separately. Tuticorin International Container Terminal opened in September 2024. JM Baxi Group operates the terminal, which has annual capacity of 600,000 TEU.
The reclaimed land, access dredging, larger turning circle and container terminal provide a wider operating base for Berth No. 10. The SCL Mercury call marks the shift from development to initial vessel operations. The opening milestone is real. The 10.22-million-tonne claim remains a design capacity until cargo data proves otherwise.
via Google News: Ports & Terminals (Source)
More from James Calloway
Show full bio
Correspondent covering technology and product news in commercial shipping for industry professionals at Vessels.
109 articles
Linked entries
- Three bidders vie for Rs 117.33bn VOC marine package
- Durban Gateway races 20-day backlog with crane repairs and 70-unit fleet order
- India Plots Five Greenfield Shipyard Clusters With $8 Billion Push
- Singapore starts work on Tuas Port's largest finger, 21 berths
- Caerus launches 14-day Oman-India container service