Supreme Court orders APM Terminals into JNPT Fourth Terminal tender
India’s Supreme Court found APM Terminals B.V.’s exclusion from JNPT’s Fourth Container Terminal tender unjustified and directed the Netherlands-incorporated bidder back into the process.

By Amara Osei
The Supreme Court has ordered APM Terminals B.V. back into the tender for development of the Fourth Container Terminal at the Jawaharlal Nehru Port Trust (JNPT), finding the exclusion unjustified. The published case note places the ruling within Paras 1-40.
JNPT’s Board of Trustees had barred the Netherlands-incorporated appellant under Clause 8.31 of the Licence Agreement and subsequent policy changes. APM Terminals had previously formed a joint venture and successfully bid for terminal operations at the port. The stated concern was the appellant’s perceived monopolistic practices.
The dispute sits against India’s shift from bulk to container handling and a central-government policy encouraging private-sector participation in ports since 1996. A 2007 policy circular later allowed existing operators to bid for new projects, sharpening the question over JNPT’s treatment of an established bidder.
What did the Supreme Court decide?
The court held that “the exclusion of APM Terminals B.V. from the tender process for the Fourth Container Terminal was not justified.” It directed that the appellant “be allowed to participate in the tender process.”
In practical terms, APM Terminals regains bidder access. The headnote says the exclusion contradicted the policy of promoting competition and preventing monopolies. It also records the appellant’s challenge as one going to competition, fairness and the Major Port Trusts Act, 1963.
Section 111 of that Act supplied the legal setting for the review. The court weighed JNPT’s contractual basis for exclusion against the policy position and concluded that the respondents had not justified keeping APM Terminals out.
Why was APM Terminals excluded?
APM Terminals argued that the Board’s decision was “arbitrary and discriminatory,” violated its contractual rights and offended principles of competition and fairness. Its earlier joint venture and successful terminal-operations bid gave it a direct operating connection with JNPT.
JNPT’s respondents took the opposite line. They maintained that exclusion was necessary to prevent monopolies, and the Board acted on Clause 8.31 of the Licence Agreement plus subsequent policy changes. The policy framework included preventing monopolies, but the court rejected exclusion as the answer in this tender.
How did the 2007 circular affect the case?
The 2007 circular allowed existing operators to bid for new projects. That mattered because the appellant came with a joint-venture and terminal-operations record, rather than approaching the Fourth Container Terminal without port experience.
The court examined Clause 8.31, subsequent policy changes and the 2007 circular together, alongside the parties’ arguments on monopoly risk. Its conclusion was that the exclusion contradicted established competition policy and was not justified.
What changes for the Fourth Container Terminal tender?
- APM Terminals B.V. must be allowed to participate in the tender.
- Clause 8.31 of the Licence Agreement and subsequent policy changes cannot sustain its exclusion.
- The Section 111 review required consistency with contractual rights, fairness and established competition policy.
The ruling also carries a broader message for public-private partnerships: the rules must be clear, the process fair, and established policies promoting competition must be followed. Clarity and fairness matter because the dispute arose from a licence clause and later policy changes being used to exclude a bidder.
APM Terminals can now bid again. For JNPT, the exclusion is gone; the ruling does not settle the tender outcome.
The gate is open again. The contract still has to be won.
via Google News: Ports & Terminals (Source)
More from Amara Osei
Show full bio
Senior reporter covering technology and product news in commercial shipping for industry professionals at Vessels.
125 articles
Linked entries
- 100% container scan deadlock strands imports at Cochin Port
- Gateway Distriparks wins eight-year JNPA common rail yard mandate
- Four bids vie for six-month Chittagong Container Terminal contract
- Gateway Distriparks takes 8-year JNPA rail yard mandate
- Fiji Cabinet backs $792m Lautoka shipbuilding and repair plan