Petrobras sends two Búzios units to Brazil, holds third at yard
Petrobras expects three 225,000-bpd floating production vessels to lift Búzios above 2 million bpd in 2027; P-80 and P-82 have left Singapore, while P-83 awaits departure.

Adjustments
- Búzios installed capacity is projected to exceed 2 million bpd in 2027, up from 1.33 million bpd.
- P-80, P-82 and P-83 each have nominal oil-processing capacity of 225,000 bpd, totaling 675,000 bpd.
- P-80 left Tuas Boulevard Yard on September 30, while P-82 left on October 18.
- P-82 was designed to compress up to 12 million cubic metres of gas per day.
- P-80 is about 345 metres long, and all three units target 2027 production.
Petrobras expects Búzios to exceed 2 million barrels per day (bpd) of installed oil capacity in 2027, up from 1.33 million, as three 225,000-bpd floating production vessels (FPVs) move toward start-up.
The state-owned oil company’s business plan, approved November 23, 2026, and presentation filed with the U.S. Securities and Exchange Commission (SEC) place all three units on the 2027 operating schedule.
Petrobras stated: “P-80 and P-82” are “en route to Brazil,” while P-83 is “preparing to leave the shipyard.” The status leaves two of the three 2027 units in transit and one awaiting departure.
Which platforms have already left Singapore?
- P-80, Búzios 9: Left Tuas Boulevard Yard in Singapore on September 30 and is en route to Brazil. The 225,000-bpd unit is about 345 metres long and carries equipment to receive, separate and process fluids from wells at Búzios 9.
- P-82, Búzios 10: Left the same yard on October 18 and is also en route to Brazil. In addition to nominal oil capacity of 225,000 bpd, the unit was designed to compress up to 12 million cubic metres of gas per day.
- P-83, Búzios 11: Was preparing to leave the shipyard in Petrobras’ November presentation. The 225,000-bpd unit is scheduled for 2027 production, and the company cited the P-83 fact sheet in its construction-contract announcement.
Petrobras’ filing links each FPV to a numbered development: P-80 to Búzios 9, P-82 to Búzios 10 and P-83 to Búzios 11. The common target concentrates three 225,000-bpd additions in one operating year. P-83’s later yard status still leaves the delivery sequence incomplete, even though all three units carry 2027 production dates.
Petrobras has grouped the three commissioning efforts into one 2027 start-up window, despite separate yard departures for P-80 and P-82. P-80 and P-82 have left the yard, while P-83 remains on the pre-departure side of that sequence.
How much capacity will reach Búzios?
Each unit’s 225,000-bpd rating represents nominal oil-processing capacity, so the three contribute 675,000 bpd on a nominal basis. Petrobras links that addition to Búzios installed capacity rising above 2 million bpd in 2027 from 1.33 million bpd. The company presents the figure as installed capacity, not a guaranteed daily production rate.
Actual output will depend on the pace at which the platforms come online and on well availability. Production can increase gradually as wells connect and each FPV’s systems stabilize, so the nominal ratings set the processing ceiling rather than immediate field throughput.
The company’s wording separates equipment availability from field performance: installed capacity counts the processing systems, while actual output follows well connections and stable vessel operations.
What happens before first oil?
Each FPV must be positioned and anchored at Búzios, connected to the well lines and tested before it can begin operations. First oil marks the start of production; output then builds gradually as additional wells connect and the vessel’s systems reach stable operation.
Delivery alone will not end Petrobras’ work. After a vessel reaches Búzios, the company must complete positioning, anchoring, well-line connection and system testing for each unit. That sequence makes offshore execution, as well as P-83’s pending yard departure, part of the path to the field’s 2027 operating target.
via Google News: Shipbuilding (Source)
More from Sophie Lindqvist
Show full bio
Market editor covering technology and product news in commercial shipping for industry professionals at Vessels.
185 articles
Linked entries
- Petrobras to consolidate STS08 area at Port of Santos by 2027
- Suape Supplies 1,040 Tonnes of B30 Biobunker in Three Days
- Brazilian Yards Land 25 New Vessel Orders on Petrobras and Transpetro Demand
- Petronas Names PFLNG TIGA, 'World's First' Nearshore FLNG Unit
- Brazil's Shipyards Head Past 80,000 Jobs on Transpetro Orders