Ports & Terminals

Montreal's Contrecœur Terminal Lands Design Team as Cost Hits C$2.3bn

Arcadis and Egis will design the landside half of Montreal's C$2.3bn Contrecœur terminal, adding 1.15m TEU of capacity by 2030 as DP World prepares to operate the St. Lawrence site.

Contrecœur Container Terminal Lines Up Landside Design as Cost Hits C$2.3bn - Construction Review
Exhibit · Contrecœur Container Terminal Lines Up Landside Design as Cost Hits C$2.3bn - Construction Review — Derks24 / pixabay

Adjustments

  1. Contrecœur terminal cost estimate has risen from C$1.6bn to C$2.3bn, with opening pushed from 2024 to 2030.
  2. The terminal will add 1.15 million TEU of annual capacity, a roughly 60% increase for the Port of Montreal.
  3. Contrecœur Terminal Constructors (60% Pomerleau, 40% Aecon) holds a C$609m design-build contract for marine works.
  4. Canada Infrastructure Bank is lending C$1.16bn; 25-30% of the funding package remained unconfirmed as of August 2026.
  5. Federal government expects 4,000 jobs a year during construction and C$750m in annual economic benefits.

The Port of Montreal's Contrecœur Container Terminal will cost C$2.3 billion and won't open until 2030, a six-year slip from the original 2024 target, as an Arcadis and Egis joint venture signs on to design the landside half of the project.

DP World, which will operate the terminal for the Montreal Port Authority, appointed the pair as Operator's Engineer. Their brief covers the buildings, container yard, rail yard, utilities and truck gates. Marine works are already underway on the St. Lawrence River site.

Once complete, the terminal adds 1.15 million twenty-foot equivalent units (TEUs) of annual capacity, lifting the port's container throughput potential by roughly 60%.

Who designs what?

The split is clean. Arcadis leads the environmental assessment, geotechnical and electrical engineering, rail infrastructure, and the terminal's main operations and administration buildings. Egis takes the utility buildings, civil utilities, crane rails, pavements and truck gate infrastructure.

Moffatt & Nichol joins as a subconsultant. It will set out terminal planning and operating specifications, which will shape the yard layout and how containers move through it.

Kevin Karaloff, who leads ports and marine work at Arcadis, described the scheme as a major investment in Canada's trade infrastructure and an important step for one of the country's key trade gateways.

How did the price reach C$2.3 billion?

When Ottawa authorized the terminal in 2021, the port authority aimed to open it by 2024, and the cost estimate stood at C$1.6 billion. Federal minister Dominic LeBlanc put the figure at C$2.3 billion in September 2025, as the port signed its development agreement with DP World's Canadian unit — a C$700 million climb on a project first priced four years earlier.

Public money covers a large share:

  • Canada Infrastructure Bank: C$1.16 billion in lending
  • Transport Canada: C$150 million
  • Government of Québec: C$130 million

Port officials said in August 2026 that 25% to 30% of the funding package remained unconfirmed, and talks on DP World's contribution continue alongside its construction and operating agreement.

When will the terminal open?

Operations are targeted for 2030. On the water, Contrecœur Terminal Constructors — owned 60% by Pomerleau and 40% by Aecon — holds a C$609 million design-build contract covering dredging, quay walls and the berths. Prime Minister Mark Carney marked the start of construction in April 2026, and the port confirmed in August that in-water work had begun.

The move downstream reflects a squeeze on the island. Transport Canada describes Montreal as the largest container port in Central and Eastern Canada, and the port authority says its existing terminals there are approaching full capacity, with little room left to grow.

The finished site will have two berths, a container yard, an intermodal rail yard linked to the CN network and a truck gate. Ottawa has designated it a project of national interest. The federal government expects it to support about 4,000 jobs a year during construction and some C$750 million in annual economic benefits once running.

Elsewhere in Canadian infrastructure, detailed design is also the current stage for Mississauga's Lakeshore Bus Rapid Transit project, where HDR and GEI Consultants are preparing a 2 km busway. City staff expect it to cost about C$89 million, with early works planned for late 2026 or early 2027.

via Google News: Ports & Terminals (Source)

Share this article:

More from Tom Whitfield

Tom Whitfield

Show full bio

Staff writer covering companies, deals and strategy in commercial shipping for industry professionals at Vessels.

198 articles

Linked entries

  1. Arcadis-Egis appointed for $2.3B Contrecœur terminal expansion
  2. Ottawa and Ontario Put $250M Into Port of Sault Ste. Marie Build-Out
  3. Lomé Container Terminal Wraps CFAF 13 Billion Quay Upgrade
  4. Manzanillo Moves 2.07 Million TEU, But Off-Dock Yards Won't Fix It Alone
  5. CICT lifts cargo handling productivity 10% with digital upgrades

▲ Previous article