Golar eyes fifth FLNG as Grace Dahlia conversion runs at Yantai
Golar LNG has reserved Seatrium yard capacity for a possible fifth FLNG, but ties the investment decision to a long-term charter for its fourth unit under conversion at Yantai.

Adjustments
- Fourth FLNG conversion sanctioned in August with CIMC Raffles at an estimated total investment of $2.45bn
- Grace Dahlia, built 2013 and acquired from NYK Line, to become a 3.5m-tonne-per-year FLNG completing in 2029
- Fifth FLNG decision hinges on a long-term employment contract for the fourth unit; Seatrium LOI covers MKI or MKII capacity
- FLNG Hilli to redeploy from Cameroon to Argentina on a new 20-year contract starting in 2027
- Amended Hilli financing expected to release about $472m in December, with a further $240m in later years subject to approvals
$2.45bn FLNG conversion of the Grace Dahlia is under way at CIMC Raffles' Yantai yard, and Golar LNG is already reserving yard capacity for a fifth floating liquefied natural gas (FLNG) unit.
The Grace Dahlia, a 2013-built LNG carrier acquired from NYK Line, now sits in the Chinese yard. Golar will convert her into a 3.5m-tonne-per-year FLNG facility, with conversion work expected to be completed in 2029. The company sanctioned the fourth project in August, awarding the contract to CIMC Raffles at an estimated total investment of $2.45bn.
What does Golar need before sanctioning a fifth FLNG?
Golar set out the groundwork in its third-quarter results. The company holds a letter of intent (LOI) with Singapore's Seatrium covering additional conversion yard capacity.
Golar is also securing long-lead equipment reservations for the same project. The Seatrium arrangement could accommodate either an MKI or an MKII FLNG design. Golar has retained further construction options at CIMC Raffles.
The gating condition is commercial, not technical. Golar said a fifth FLNG investment decision "would depend on securing a long-term employment contract for its fourth unit." Yard space is reserved. The sanction is not.
No capital figure and no sanction date attach to a fifth unit yet. Golar presents the preparations as a response to growing demand for offshore gas production capacity.
Who wants the fourth unit?
Golar said it is "advancing commercial discussions" for the fourth FLNG. Interest has been strongest from South America and West Africa, and both regions point at the same 3.5m-tonne-per-year capacity.
No charterer name, contract length or start date has been disclosed. Until one is signed, Golar's own sequencing puts a long-term employment contract for the fourth unit ahead of any fifth-unit decision.
What changes for FLNG Hilli?
Hilli is moving continents. Golar is preparing to redeploy the vessel from Cameroon to Argentina after an upgrade programme at Seatrium's Singapore yard. A new 20-year contract is expected to begin in 2027.
The financing follows the redeployment. An amended financing arrangement is expected to release approximately $472m in liquidity in December. A further $240m could become available in subsequent years, subject to additional approvals.
Where the FLNG pipeline stands
- Fourth unit: $2.45bn estimated total investment, sanctioned in August, contract with CIMC Raffles.
- Grace Dahlia: built 2013, acquired from NYK Line, 3.5m tonnes per year, conversion completes 2029.
- Fifth unit: no sanction and no cost figure; Seatrium LOI plus CIMC Raffles options, MKI or MKII design.
- Hilli: 20-year contract in Argentina from 2027, replacing the Cameroon deployment.
- Hilli refinancing: about $472m of liquidity in December, plus $240m in later years pending approvals.
Three units, two yards, three clocks. Seatrium in Singapore holds the Hilli upgrade and Golar's letter of intent for a fifth conversion. CIMC Raffles in Yantai holds the Grace Dahlia work and the spare construction options. The fourth unit still needs a charter before the fifth can be sanctioned, and Golar is shopping that 3.5 million tonnes per year first to South America and West Africa.
Golar has not disclosed which yard would take a fifth conversion, what it would cost, or when a final investment decision might land. Its fourth unit, by contrast, already carries a price tag and a completion date.
via Splash 247 (Source)
More from Tom Whitfield
Show full bio
Staff writer covering companies, deals and strategy in commercial shipping for industry professionals at Vessels.
43 articles
Linked entries
- Jiangnan begins 175,000 m³ LNG carrier series for Shell
- Stamford firms 10 MR tankers at CIMC SOE, European owner adds two more
- GTT wins five-vessel MISC LNG tank order at Hudong-Zhonghua
- Sinogas in talks with Jiangnan for two VLACs as gas orderbook nears 40% of fleet
- COSCO pays RMB570m for 146 hectares to build Tianjin mega-yard