Ports & Terminals

Portonave reopens 900m quay for 400m boxships after R$1.5bn rebuild

BESIX confirmed on November 20, 2026 the R$1.5bn, 900-meter quay rebuild at Portonave's Navegantes terminal — done without halting cargo, and rated for 400m boxships once channel dredging lands.

Brazilian port completes R$1.5 billion project, rebuilds 900 meters of quay without halting operations, and prepares to
Exhibit · Brazilian port completes R$1.5 billion project, rebuilds 900 meters of quay without halting operations, and prepares to — Julia Taubitz / unsplash

Adjustments

  1. Portonave completed a R$1.5 billion rebuild of 900 meters of quay at Navegantes on November 20, 2026, without interrupting terminal operations.
  2. Bored piles reached 60 meters deep; nine million work hours were logged without a serious incident.
  3. Throughput reached 868,427 TEUs in January-August 2026, up 23% year on year.
  4. Two ZPMC electric cranes worth R$229 million arrived November 14; capacity will rise from 1.5 to 2 million TEUs per year.
  5. 400-meter ships still await channel dredging; Antaq removed the concession vote from its agenda on November 12, 2026.

Portonave has finished a R$1.5 billion rebuild of all 900 meters of quay at Navegantes, Santa Catarina, without a single day of closed gates — and the structure is now rated for ships up to 400 meters long.

Belgian contractor BESIX, better known for the Burj Khalifa, confirmed completion on November 20, 2026. The work ran nearly three years on a live terminal, which is the part engineers will argue about at conferences for a while.

How do you rebuild a quay while ships keep berthing?

Engineers split the 900-meter frontage into two 450-meter sections. One half took the ships; the other took the excavators. Permanent construction began in January 2024.

The sequence was old-school and heavy. Before demolishing the existing structures, crews stabilized the ground with rockfill — large rock blocks reinforcing the subsoil. Then Franki Foundations, BESIX Group's deep-foundations specialist, installed bored piles reaching 60 meters below ground level. Those piles carry both the quay's equipment loads and the forces from ships docking alongside.

Safety numbers held up. BESIX reports nine million work hours logged without a serious incident, on a site where construction zones sat next to operating berths.

What happened to the cranes?

October 2025 delivered the delicate bit. The first 450 meters were done, and six large port cranes had to shift onto the new section to clear the second-phase working area. The move took two days, per the contractor.

The terminal did pay a price in berth availability during the works. On August 18, 2026, completion of another 250 meters brought the operational quay to 700 meters — that day, CMA CGM Thorium and Mercosul Suape resumed simultaneous operations. With the rebuild complete, Portonave can again work up to three vessels at once.

Throughput grew anyway. January-August 2026 saw 868,427 TEUs pass the terminal, up 23% year on year. Building sites, it turns out, don't scare cargo owners.

What comes with the new quay?

The rebuild is one piece of a modernization program worth more than R$2 billion in infrastructure and equipment.

  • On November 14, two new electric ship-to-shore cranes from China's ZPMC arrived, purchased for R$229 million.
  • Each crane stands 55 meters tall and lifts up to 100 metric tons, sized to reach containers stowed on large vessels.
  • Portonave expects both in service by December 31, after tests and training.
  • Annual terminal capacity rises from 1.5 million to 2 million TEUs once the program wraps — a 33% increase.

The new quay was also designed to take a future shore power system, so berthed vessels can shut down their auxiliary engines instead of burning fuel at the berth.

Can 400-meter ships actually call?

Not yet. The quay is ready; the channel is not.

Access to the Itajaí and Navegantes port complex still depends on dredging and rock removal in the channel and turning basin, under a concession project. On November 12, 2026, Antaq pulled the vote from its agenda at the request of the Ministry of Ports and Airports, which wants further review of the dredging studies. Anyone tracking Brazil's port timelines knows what that means.

Under the federal plan presented in June, initial works would allow ships up to 366 meters. Vessels of 400 meters — the largest in international container trade — would wait until the fourth year of the future concession.

So Portonave has the quay, the cranes and the numbers. The 400-meter ships will come when the channel lets them.

via Google News: Ports & Terminals (Source)

Share this article:

More from Amara Osei

Amara Osei

Show full bio

Senior reporter covering technology and product news in commercial shipping for industry professionals at Vessels.

211 articles

Linked entries

  1. Singapore starts work on Tuas Port's largest finger, 21 berths
  2. Lomé Container Terminal Wraps CFAF 13 Billion Quay Upgrade
  3. J M Baxi Group buys 51% of San Maritime, enters shipbuilding
  4. India Clears 2 M TEU Second Container Terminal at Kamarajar Port
  5. Manzanillo Moves 2.07 Million TEU, But Off-Dock Yards Won't Fix It Alone

▲ Previous article