Charter & Freight Markets

Asia project cargo demand set to surge, but roads lag

Asia’s project cargo pipeline is set to expand, but 500-1,500-tonne modules, weak roads and late logistics planning still threaten port-to-door schedules.

Project cargo boom in Asia hobbled by inadequate infrastructure
Exhibit · Project cargo boom in Asia hobbled by inadequate infrastructure — pixel2013 / pixabay

Adjustments

  1. Demand for Asian project cargo is expected to surge in the near term.
  2. Denzai identifies modules weighing 500-1,500 tonnes as a road and bridge bottleneck.
  3. AAL Shipping traces the EPC shift to China Plus One over the past 10 years.
  4. Clients now seek logistics approval before purchase orders are signed.
  5. Speakers disclosed no cargo-volume, freight-rate, schedule or infrastructure-investment figures.

By James Calloway

Modules weighing 500 to 1,500 tonnes are exposing the infrastructure gap behind Asia’s expected near-term project cargo surge, as transport capacity struggles to keep pace with project development.

No speaker at Breakbulk Asia in Singapore disclosed expected cargo volumes, tonnages, freight rates or delivery dates. The boom claim therefore remains directional, not yet a number shipowners, charterers or port operators can plan around.

What is driving Asia’s project cargo boom?

MSC’s head of project cargo, Ben Collins, said Asia is becoming more important to executing major infrastructure and industrial projects. He said:

“Vietnam has an emerging nuclear power programme; Asia is very central to the supply and successful delivery of these projects, so it’s time for optimism and bullishness.”

He offered no cargo volume, project schedule or reactor delivery date to size that opportunity.

AAL Shipping commercial chief Felix Schoeller said geopolitical developments accelerated the relocation and expansion of engineering, procurement and construction activities across Asia. He tied that shift to the past 10 years, including the first Trump administration, and the China Plus One strategy.

That strategy, he said, increased manufacturing capacity across South-east Asia and India. The panel, however, offered no project list, cargo breakdown or production forecast to show how much of that capacity will require project cargo shipping.

Where can the route fail?

Kohki Uemura, CEO of Japanese heavylift forwarder Denzai, identified roads and bridges as the main bottleneck for modules weighing 500 to 1,500 tonnes. His blunt assessment was:

“Roads and bridges are not enough for such heavy cargo.”

Other executives warned that inadequate landside infrastructure and broader logistical constraints could delay oversize and heavy cargo movements. The issue extends beyond ship-to-quay handling. Cargo still has to reach its final destination.

Yohan Beal, Ceva Logistics’ operations director for Asia Pacific, assigned responsibility to parties conducting logistics surveys and overseeing project requirements. He asked whether due diligence establishes that cargo can leave the discharge port and reach the destination before the discharge port and final route are fixed.

A 500-tonne module already tests road and bridge limits; a 1,500-tonne module leaves operators less room for error. The speakers offered no bridge-load ratings, axle limits, road closures or upgrade timetables, so route feasibility remains a project-by-project question rather than a standard quotation.

When should logistics join the project?

Beal said project owners and EPC contractors now recognise logistics earlier in planning and involve specialist providers sooner. Since the pandemic, he said, previously underappreciated logistics staff have reached boardrooms, while clients seek approval before purchase orders are signed.

Collins echoed the call for earlier planning. He cautioned project owners against chasing a cheaper transport price tomorrow when the cargo selected today may cost more to move later. His warning treats transport requirements as part of the purchase decision, not a downstream booking problem.

The governance change could prevent an expensive assumption from becoming a heavier operational problem. Early approval still cannot repair a deficient road or bridge. None of the speakers said which ports, projects or cargo owners have adopted the new approval process.

For shipowners and charterers, the useful signal is tighter coordination before cargo contracts close. The missing data are the cargo pipeline, route capacity and delivery schedule that would convert the panel’s optimism into firm port calls and transport demand.

via The Loadstar (Source)

Share this article:

More from James Calloway

James Calloway

Show full bio

Correspondent covering technology and product news in commercial shipping for industry professionals at Vessels.

30 articles

Linked entries

  1. India Dangles $10 bn Shipbuilding Pitch at Global Yards and Lines
  2. Samsung Heavy Eyes India as Korean Yards Book Out to 2028
  3. Suspended Section 301 Port Fees on Chinese Ships Left Off Trump-Xi Agenda
  4. Samsung Heavy Industries eyes India with yard booked for 3 years
  5. India Chases $10 Billion to Build Five Shipyard Clusters

▲ Previous article