Regulation & Policy

Appeals Court Voids ROD Behind Sentinel's $2.1bn GulfLink License

Fifth Circuit voided the ROD behind Sentinel Midstream's $2.1bn Texas GulfLink export license, citing illegal overlap with Enterprise's SPOT. Offshore work stalls; Supreme Court petition planned.

Court Ruling Threatens License for $2.1 Billion Texas Offshore Oil Export Project
Exhibit · Court Ruling Threatens License for $2.1 Billion Texas Offshore Oil Export Project — wasi1370 / pixabay

Adjustments

  1. Fifth Circuit voided the ROD for the $2.1bn Texas GulfLink project; ruling took effect October 30.
  2. License issued January 2026; FID in May; target start-up Q4 2028, 30 miles off Freeport.
  3. Court found application area overlapped Enterprise's SPOT, violating the Deepwater Port Act.
  4. Prior approval took nearly seven years; MARAD's recent pace is 410 days per license.
  5. GulfLink design: fully load a 2-million-barrel-per-day supertanker.

A US appeals court has voided the record of decision underpinning Sentinel Midstream's $2.1 billion Texas GulfLink deepwater crude export terminal, and the ruling took effect October 30. The license itself now hangs on MARAD's next move, and offshore construction cannot lawfully proceed on it, petitioners say.

The Fifth Circuit Court of Appeals ruled in August that MARAD's record of decision violated the Deepwater Port Act, which allows only one approved deepwater port per application area. Texas GulfLink's area, properly designated, intersects with Enterprise Products Partners' Sea Port Oil Terminal (SPOT) project. The court held that Congress struck a careful balance between promoting and regulating deepwater ports, and that an application area must cover the entire proposed port site, including any proposed pipeline.

What does the ruling change?

Everything offshore, practically speaking. MARAD approved Texas GulfLink with conditions in its ROD last year, and Sentinel received its license in January 2026. The company took final investment decision in May and began construction.

Now the legal floor has dropped out. "The Court's decision is clear: it vacated the record of decision that was the foundation of GulfLink's license. Now, MARAD has to revoke or suspend that license," Michael Brown, counsel for the petitioners, said Wednesday. Better Brazoria Clean Air and Water, the environmental group behind the petition, says construction cannot continue without a federal deepwater port license.

A source with knowledge of the situation put it flatly: "Sentinel is working with MARAD to discuss its options for moving forward. The company cannot continue with the current license." MARAD said it was disappointed and continues to pursue all avenues toward the President's vision of American energy dominance. Sentinel told Reuters its license has not been suspended or terminated.

Is it really "business as usual"?

Sentinel says yes. Bruce Heine, senior vice president, said this week the project remains on track for fourth-quarter 2028 operations roughly 30 miles off Freeport, Texas. "Given the narrow nature and scope of the issue, there are multiple paths to address the statutory concern without disrupting ongoing construction activities or overall project schedule," Heine said.

Site development is underway at the Jones Creek onshore terminal, tank construction is next, and major long-lead equipment, pipe and key construction contracts are already locked in, Heine said. That's the onshore half. The offshore half is the problem.

Sentinel's own court filing last month, seeking a stay of the mandate, concedes the point. The license expressly incorporates the ROD as a compliance standard, the company argued, so voiding the ROD exposes the license to suspension or revocation and prevents construction of offshore components. "At a minimum, the cloud on Texas GulfLink's regulatory posture will harm Texas GulfLink in the marketplace," the motion said. It added the project "will not commence construction of the deepwater port under the current posture, even if the mandate is stayed." The public line and the filing don't quite match.

What happens next?

Sentinel plans to petition the Supreme Court, per its motion. The company also flagged that two other pending deepwater port applications have areas similar to GulfLink's and will likely require redesignation, with what it called consequential impacts on those projects.

If MARAD forces a resubmission, Sentinel waits for a new ROD and license. The first round took nearly seven years, though MARAD has accelerated under President Trump — a recent deepwater license took just 410 days, roughly 3.7 years faster than the historical average.

Texas GulfLink is designed to fully load a supertanker with about 2 million barrels per day. The administration has recently approved licenses for Energy Transfer's Blue Marlin Offshore Port off Louisiana and ST LNG's Texas LNG shipping project — both now sitting under the same statutory question the Fifth Circuit just raised.

via gCaptain (Source)

Share this article:

More from James Calloway

James Calloway

Show full bio

Correspondent covering technology and product news in commercial shipping for industry professionals at Vessels.

66 articles

Linked entries

  1. Steer acquires Mercator consultancy in fourth deal since 2021
  2. MARAD delegation tours HD Hyundai Heavy's Ulsan yard
  3. Phillips 66 Los Angeles berth plan enters draft environmental review
  4. MARAD deputy tours HD Hyundai Heavy's Ulsan yard
  5. MARAD delegation tours HD HHI Ulsan yard as Bridge Strategy opens US naval work

▲ Previous article▼ Next article